FEATHER RIVER AIR QUALITY MANAGEMENT DISTRICT
RULE 4.9 - ACTION ON APPLICATION
(Adopted 8/91)
The applicant may, at his option, deem the Authorization to Construct or Permit to Operate denied if the APCO fails
to act on the application within thirty (30) days after applicant furnishes the further information, plans and
specifications requested by the APCO, whichever is later.