FEATHER RIVER AIR QUALITY MANAGEMENT DISTRICT
RULE 9.5 - AIR POLLUTION EQUIPMENT - SCHEDULED MAINTENANCE
(Adopted 6/91)
In the case of shut-down or re-start of air pollution equipment for necessary scheduled maintenance, the intent
to shut down such equipment shall be reported to the Air Pollution Control Officer at least twenty-four (24) hours
prior to the planned shutdown. Such prior notice may include, but is not limited to the following:
- Identification of the specific facility to be taken out of service as well as its location and permit number;
- The expected length of time that the air pollution control equipment will be out of service;
- The nature and quantity of emissions of air contaminants likely to occur during the shut-down period;
- Measures such as the use of off-shift labor and equipment that will be taken to minimize the length of the
shut-down period;
- The reasons that it would be impossible or impractical to shut down the source operation during the maintenance
period: During the testing period moderate emission of air pollution may be allowed.