GREAT BASIN UNIFIED AIR POLLUTION CONTROL DISTRICT
RULE 210 - CONDITIONAL APPROVAL
(Adopted 8/20/79)
A. The Air Pollution Control Officer may issue an authority to construct or a permit to operate or use, subject
to conditions which will assure the operation of any article, machine, equipment or other contrivance within the
standards of Rule 209 in which case the conditions shall be specified in writing. Commencing work under such an
authority to construct or operation under such a permit to operate shall be deemed acceptance of all the conditions
so specified. The Air Pollution Control Officer shall issue an authority to construct or a permit to operate with
revised conditions upon receipt of new application, if the applicant demonstrates that the article, machine, equipment
or other contrivance can operate within the standards of Rule 209 under the revised conditions.
B. The Air Pollution Control Officer shall, as condition for the issuance of an authority to construct for a new stationary source or modification and with prior written consent of the owner or operator of any source which provides offsets:
C. Annual Review of Conditions
Upon annual renewal, each permit to operate will be reviewed to determine that permit conditions are adequate to ensure compliance with, and the enforceability of, District rules and regulations applicable to the source for which the permit was issued which were in effect at the time the permit was issued or modified, or which have subsequently been adopted and made retroactively applicable to an existing source by the District board and, if the conditions are not consistent, the permit will be revised to specify the permit conditions in accordance with all applicable rules and regulations.