SAN DIEGO COUNTY AIR POLLUTION CONTROL DISTRICT

RULE 260.673 - RECONSTRUCTION

(a) The cost of replacement of ore-contact surfaces on processing equipment shall not be considered in calculating either the "fixed capital cost of the new components" or the "fixed capital cost that would be required to construct a comparable new facility" under Rule 260.15. Ore-contact surfaces are crushing surfaces; screen meshes, bars, and plates; conveyor belts; and elevator buckets.

(b) Under Rule 260.15, the "fixed capital cost of the new components" includes the fixed capital cost of all depreciable components (except components specified in Section (a) of this rule) which are or will be replaced pursuant to all continuous programs of component replacement commenced within any 2-year period following August 31, 1983.