SAN JOAQUIN VALLEY UNIFIED AIR POLLUTION CONTROL DISTRICT
RULE 5050 - COMPLIANCE SCHEDULE
(Adopted May 21, 1992; Amended December 17, 1992; Amended December 16, 1993)
1.0 Requirements
1.1 A compliance schedule shall be prepared by the petitioner for a variance and filed with the petition for a variance not less than 30 days prior to the hearing. The compliance schedule shall be retained for public inspection at the office of the District.
1.2 The compliance schedule shall include the following minimum increments of progress:
1.2.1 Submission of final control plans.
1.2.2 Date of issuance of the contract for construction or process changes.
1.2.3 Date of initiation of construction or process change.
1.2.4 Date for completion of construction or process change.
1.2.5 Date for initial start-up of process and control systems.
1.2.6 Date for performance tests on control systems and processes, if applicable.
1.2.7 Date for final compliance with rule for which variance is to be granted.
1.3 Any owner or operator who submits a compliance schedule shall certify in writing to the Air Pollution Control District within 5 days of each increment of progress specified in section 1.2 above, whether or not the required increment of progress was achieved. Failure to submit such certification or to achieve such increment may be cause to invalidate any variance granted to the petitioner and may cause the revoking of Permits to Operate granted by the APCO.