Permit Streamlining Guidance Document
This page last reviewed January 11, 2011
ABSTRACT
Air pollution control districts and air quality management districts
in California are actively working to streamline the permitting process so
businesses can obtain permits more quickly, without compromising air
quality. This document, prepared by the California Air Pollution Control
Officers' Association and the California Air Resources Board, describes
ongoing and planned district programs to expedite permitting. It also
identifies measures the regulated community considers critical for improving
the air permitting process. The document is intended to serve as a
reference for districts to use in developing or expanding programs to
streamline permitting.
The document describes improvements districts have made in almost all
aspects of the permitting process, including changes to application forms,
in the way forms are submitted, in the way districts conduct evaluations of
projects, and in the way permits are prepared. Some of these improvements
are associated with requirements of the Air Pollution Permit Streamlining
Act (Health and Safety Code sections 42320-42323; AB 2781), but the majority
are measures that go well beyond those requirements and satisfy needs
specific to the individual districts. The document also describes other
district activities that may not necessarily expedite permitting, but
improve the overall process.
Appendices referenced in this document contain more detailed descriptions of
district programs and examples of district permitting materials. For
copies of the appendices, please contact:
Permit Assistance Section Stationary Source Division
California Air Resources Board
P.O. Box 2815
Sacramento, CA 95812
(916) 322-2825
or
1-800-ARB-HLP2
PERMIT STREAMLINING GUIDANCE DOCUMENT
Table of Contents
Page
I. INTRODUCTION . . . . . . . . . . . . . . . . . . . . . . . . . . . 1
II. BACKGROUND . . . . . . . . . . . . . . . . . . . . . . . . . . . . 6
A. The Air Permitting Process . . . . . . . . . . . . . . . . . . 6
B. Permit Streamlining . . . . . . . . . . . . . . . . . . . . . 8
III. AIR POLLUTION PERMIT STREAMLINING ACT (AB 2781) . . . . . . . . . 10
A. General Requirements . . . . . . . . . . . . . . . . . . . . . 10
B. Precertification of Commonly Used Equipment . . . . . . . . . 11
C. Consolidated Facility Permitting . . . . . . . . . . . . . . . 13
D. Expedited Permitting for Minor, Moderate and Major Sources . . 14
E. Training and Certification Program . . . . . . . . . . . . . . 16
F. Standardized Application Forms . . . . . . . . . . . . . . . . 18
G. Combined Authority to Construct and Permit to Operate . . . . 19
H. Appeals Process . . . . . . . . . . . . . . . . . . . . . . . 20
I. Small Business Assistance Program . . . . . . . . . . . . . . 20
IV. OTHER STREAMLINING EFFORTS . . . . . . . . . . . . . . . . . . . . 22
A. Assist Applicants in Submitting Complete Applications . . . . 22
B. Applications: Acknowledge Receipt and Expedite Review . . . . 24
C. Increase Permit Processing Efficiency . . . . . . . . . . . . 25
D. Increase Efficiency of District CEQA Review . . . . . . . . . 31
E. Reduce the Number of Permits Processed . . . . . . . . . . . . 31
F. Improve Communication with the Regulated Community . . . . . . 33
G. Coordinate with Other Agencies . . . . . . . . . . . . . . . . 36
H. Other Efforts to Improve Air Programs . . . . . . . . . . . . 38
V. COMMENTS FROM CAPCOA/ARB PUBLIC WORKSHOP ON PERMIT STREAMLINING . 41
APPENDICES*
A. District and Air Resources Board Contacts for Permit Streamlining
B. Flowcharts of Generalized Permitting Process
C. Legal Requirements Related to Permit Streamlining
D. Equipment Certification Program
E. Expedited Permitting for Minor, Moderate and Major Sources
F. Training and Certification Program
G. Air Quality Training Programs
H. Air Resources Board Course Descriptions
I. Pre-Application Forms
J. Standard Completeness Letters and Information Sheets
K. Sources Included in Permit Processing Handbooks
L. Permitting Criteria
M. CAPCOA Recommendations for District Permit Exemptions
N. Brochures and Permit Assistance Materials
O. Permit Processing Surveys
P. Proposed Plan for Developing a Small Business Assistance Program
Q. Coordination with Building/Planning Departments
R. Reporting and Recordkeeping
S. Proposal for Streamlining Permitting and Recordkeeping
Requirements
* Appendices are available from the Air Resources Board, see ABSTRACT above.
I.
INTRODUCTION
What is the purpose of this document?
The purpose of this document is to share information among the Air
Pollution Control Districts (APCDs) and Air Quality Management Districts
(AQMDs) on the types of programs that can be implemented to streamline the air
permitting process. It also identifies measures the regulated community
considers critical for improving permitting. Individual districts may use
this information as a reference for developing or expanding programs to
expedite permitting in their district.
This guideline document describes ongoing and planned district programs
to expedite the air permitting process. A number of districts have made
changes in the way they process permit applications in order to reduce the
time it takes for businesses to get a permit, without compromising air
quality. These changes are designed to make the existing permitting system
operate more efficiently; they do not change the laws that protect air quality
or the basic structure of the air permitting process. Although these
activities were developed independently by districts in response to their
individual needs, other districts may benefit from similar programs.
One area where sharing of information could be particularly valuable is
in meeting the requirements of the Air Pollution Permit Streamlining Act
(Health and Safety Code sections 42320-42323; AB 2781, Sher). This Act
requires the largest districts (i.e., those with a population greater than
250,000) to adopt, by regulation, expedited permitting systems which include
specific elements (see Chapter III). Some districts currently have or are
planning to implement programs to satisfy those requirements. Their
experience may be valuable to other districts that must also comply with the
Act.
To obtain input from the regulated community on how the permitting
process should be improved, a public workshop was held on October 28, 1993.
Industry representatives assisted the California Air Pollution Control
Officers' Association (CAPCOA) and the California Air Resources Board (ARB) in
planning and conducting the workshop. Representatives from businesses, other
regulated entities, consultants, districts, and other agencies provided
extensive comments on changes that could be made to improve the permitting
process. These comments are contained in Chapter V.
Who prepared this document?
Staff of the ARB prepared this document at the request of the CAPCOA Permit Streamlining Committee. The Permit Streamlining Committee consists of representatives of local Air Pollution Control Districts and Air Quality Management Districts, and the ARB. Information contained in the document is based on two surveys of the 34 air districts in the state, permitting program descriptions and materials provided by districts, and extensive discussions with the Permit Streamlining Committee and other air districts. Comments from the regulated community were obtained at the CAPCOA/ARB public workshop on permit streamlining.
What aspects of the permitting process are being streamlined?
Most streamlining measures apply to the processing of applications for an
authority to construct a new or modified facility. The authority to construct
is the first of a two step process for operating a source that has the
potential to emit air pollutants. As described in Section II.A., the process
for issuing an authority to construct requires the applicant to submit
project-specific information to the district and for the district to evaluate
the proposed project relative to district rules and regulations. This process
can be fairly lengthy and is the critical step in obtaining the necessary air
permits for a facility to operate. The second step, the permit to operate, is
issued after the applicant demonstrates that the facility is operating in
compliance with district rules and regulations, and in accordance with the
conditions of the authority to construct.
Districts have made changes, some relatively minor and others fairly
major, in almost all aspects of the authority to construct process. These
modifications are the result of careful evaluation by the districts of their
permitting programs to determine where beneficial changes could be made
without compromising air quality. Modifications have been made to application
forms, in the way the forms are submitted, in the way the district conducts
its evaluation of the project, and in the way permits are prepared. While
some of the measures may not appear significant when viewed separately, taken
together and multiplied by the number of applications processed, the overall
effect is to expedite permitting.
Many of the streamlining measures are designed to speed up the authority
to construct process for small sources. Small sources, such as dry cleaners
and spray booths, are fairly standard and can be evaluated quickly using
standardized approaches. By reducing the staff time involved in processing
applications for small sources, more district resources are available to
process applications for larger sources. Therefore, the overall permitting
efficiency improves.
What are key programs to streamlining the air permitting process?
Key programs described in this document include both measures required by the Air Pollution Permit Streamlining Act (Chapter III) and additional measures districts are implementing (Chapter IV). These are summarized below in the order they appear in the document.
- Pre-certification allows for quick permitting of simple, commonly used equipment that has been previously evaluated by the district.
- Expedited permitting of minor, moderate, and major sources allows for faster permitting of smaller sources while maintaining more lengthy review time necessary for larger, complex sources.
- Standardized application forms specific to source types make it easier for the applicant to submit all information necessary for an application to be deemed complete.
- Pre-application meetings improve communication between districts and applicants regarding the permitting process, information required in the application, and likely permit conditions.
- Identifying a district contact and application number, together with district tracking systems, make it easier for applicants to follow the progress of their applications through the permitting process.
- Expediting the initial review of applications for completeness and clearly identifying missing information enable applicants to complete their applications sooner.
- Standard policies, procedures, control technologies, and permit conditions let applicants know up front what will be required for their project and how to submit an application that can be quickly permitted.
- Use of computers allows for tracking applications, greater standardization of district evaluations and permits, and expedited permitting, including over-the-counter permitting.
- A statewide program for portable equipment being developed by CAPCOA will reduce the need for multiple permitting of equipment that is operated in more than one location in the state.
- Improved communication includes several of the measures listed above as well as informational brochures, workshops, client feedback, and small business assistance programs.
- Coordination with other agencies reduces potential duplication or conflict in permitting and inspections.
- Streamlining recordkeeping and reporting would make requirements simpler and more commensurate with emission potential.
What are the recommendations of the regulated community?
A CAPCOA/ARB public workshop was held on October 28, 1993, to obtain
comments on how districts could streamline the permitting process and which
measures should be highest priority. The workshop was attended by
representatives from businesses and other regulated entities, consultants, air
districts, the ARB, and other agencies. To allow for maximum participation,
the workshop included "break-out" sessions facilitated by industry
representatives. A pre-workshop meeting was held with the facilitators and
other industry representatives to plan the workshop and identify key concerns
in permit streamlining. Extensive comments were received at the workshop and
the pre-workshop meeting; many comments supported measures already being
implemented and described in this document, and others offered new ideas.
Based on the comments received, the issues of primary concern to the regulated
community can be grouped into three areas: improved communication, expedited
permitting, and greater standardization within districts and statewide.
Improved communication is a broad category that encompasses a number of
efforts districts are pursuing to help the regulated community understand the
districts' programs, obtain permits, and operate in compliance with district
rules and regulations. The regulated community would like to see districts
expand those efforts and, in addition, adopt a non-adversarial "customer
service" attitude. Participants supported the use of pre-application
meetings, permitting manuals, application tracking mechanisms, brochures,
workshops, and economic development corporations to help business understand
permitting and compliance requirements. Suggestions were made to involve
industry early in the development of new regulations, to have more interactive
workshops that allow for increased industry input to the process, and to give
industry early warning about district programs that may affect long-term
industry plans. Workshop participants also urged districts to use more
advanced communication technologies, such as E-mail, computerized bulletin
boards, electronic data submittal, and integrated databases.
Expedited permitting was identified as a high priority to the workshop
participants. There was support for tiered permitting and precertification
programs that are being implemented in some districts. Workshop participants
would like to see precertification programs expanded to include more equipment
and to be made uniform among districts. The idea of expediting critical
applications for an increased fee was also encouraged, if the program would
not slow permitting of other sources.
Workshop participants recommended more standardization within and between
districts. For example, it would be easier for the regulated community if
application forms, permitting policies and procedures, emission control
requirements and reporting requirements could be more uniform.
Workshop comments are listed in Chapter V and noted throughout the
document.
Do the streamlining measures in this document apply to all districts?
While the intent of this document is to share information about ongoing permit streamlining programs, it should not be assumed that all programs would expedite permitting in all districts. Districts differ substantially in the number and types of permits they issue; very small districts may process as few as one or two applications each year, while the largest district processes about 20,000 applications each year. Smaller districts typically do not require permits for smaller sources; in larger districts, half or more of the applications they receive are for smaller sources. Some of the streamlining measures described in this document require substantial staff time to develop. Since large districts process so many applications, the time spent in developing many of the streamlining measures discussed in this document is more than made up by the reduced time needed for processing individual permit applications. However, this may not be true for all districts. For example, a program that may expedite permitting in one district could slow permitting in another district where it is not needed.
Are there streamlining efforts not included in this document?
The programs described in this document, for the most part, represent streamlining efforts at the districts who participate in the CAPCOA Committee on Permit Streamlining. Those districts are among the larger districts in the state. Therefore, this document may not represent all streamlining efforts ongoing at the districts, particularly smaller districts. Omission of any district programs does not reflect on the value of those programs.
How is this document organized?
Chapter II provides background on the air permitting process in
California and the need to streamline that process. Chapters III and IV
summarize ongoing and planned district activities to expedite permitting. Specifically, Chapter III describes the requirements of the Air Pollution
Permit Streamlining Act, and district activities that are consistent with
those requirements. Chapter IV describes additional efforts districts are
making to streamline permitting and other district activities which are not
necessarily designed to expedite permitting, but also improve the permitting
process. Chapter V lists comments received at the CAPCOA/ARB public workshop
on permit streamlining.
The text of the document summarizes the different streamlining measures.
More complete descriptions of district programs and examples of district
permitting materials are contained in appendices which can be obtained from
the ARB at the address listed inside the cover of this document. Additional
documents, such as application forms and standardized permit conditions, are
available from individual districts and, where noted, from the ARB.
II.
BACKGROUND
A. THE AIR PERMITTING PROCESS
To provide a framework for the discussion of streamlining measures in
Chapters III and IV, this section summarizes the legal requirements and
typical process for permitting stationary sources of air pollution in
California.
The Health and Safety Code gives the Air Pollution Control Districts and
Air Quality Management Districts responsibility for permitting new and
modified facilities, consistent with the attainment and maintenance of air
quality standards. Section 42300 et seq. of the Health and Safety Code
requires that the district permit system:
a. ensure that permitted sources will not prevent or interfere with
attainment or maintenance of any applicable air quality standard;
b. prohibit the issuance of a permit until the air pollution control
officer is satisfied that the source will comply with all applicable
orders, rules and regulations of the district and of the state;
c. require that each permit be reviewed annually to determine that
permit conditions are adequate to ensure compliance with and
enforceability of district rules and regulations; and
d. provide for the reissuance or transfer of a permit to a new owner or
operator of the source.
District rules and regulations define the procedure and criteria
districts use in permitting facilities. Although specific rules vary by
district, the general procedure for permitting sources is the same throughout
the state. Applicants must obtain an authority to construct before beginning
construction, and a permit to operate after the completed facility
demonstrates compliance with district rules and regulations and the facility's
permit conditions. The following paragraphs summarize the process common to
most districts; this information is also presented in "Flowcharts of
Generalized Permitting Process" (see Figures 1 and 2 in Appendix B).
1. Submittal of Application for an Authority to Construct
The air permitting process for new and modified sources begins with the
submittal of an application for an authority to construct. The required
contents of an application typically include the following: a description of
the project and the basic equipment, calculated emissions from each
component and total emissions from the project, description of air pollution
control technology, air quality analyses, and any proposals for air quality
impact mitigation.
2. District Review of Application for an Authority to Construct
Once an application for an authority to construct is submitted, the
district has 30 days to determine if the application is complete. If the
application is not complete, the district will inform the applicant of what
additional information is needed. The applicant can then add to or modify the
application and resubmit it to the district.
After an application is deemed complete, the district prepares an
engineering analysis. This analysis documents emissions calculations,
compliance with district and state air quality regulations, assumptions used
to evaluate the acceptability of the project, and conditions of design and
operation required to achieve and maintain compliance.
3. The CEQA Process in Permitting
Before the district can issue or deny a permit for a project which may
have a significant effect on the environment, the project must comply with the
California Environmental Quality Act (CEQA). The purpose of CEQA is to ensure
that a project's environmental impacts and alternatives are disclosed to
governmental decision-makers and the general public, and that any impacts are
mitigated to the maximum extent feasible. The CEQA applies to governmental
decisions that require the exercise of judgement or deliberation (i.e.,
"discretionary activities"), as opposed to decisions involving only objective
measurements without the use of personal subjective judgement regarding the
wisdom or manner of carrying out a project. In addition, CEQA does not apply
to statutorily or categorically exempt projects, which are defined in CEQA and
the CEQA Guidelines (14 CCR section 21000 et seq.). If CEQA does apply to a
project, the lead agency, typically the local land use agency, oversees the
preparation of a negative declaration or an environmental impact report (EIR).
After the document is subject to public review and approved by the lead
agency, the district must review the environmental document and make
appropriate findings prior to making its decision on the application.
4. Issuance of an Authority to Construct
Under state law, the district must make a decision to approve or
disapprove an application for an authority to construct within a set period of
time. If CEQA is triggered, the district must make its decision within one
year (if the district is the lead agency) or 180 days (if it is a responsible
agency) from the date the EIR is certified or the application is deemed
complete, whichever is later. If CEQA does not apply, the district has 180
days after the application is deemed complete.
If a proposed project complies with all district rules and regulations
and CEQA is satisfied, the district issues an authority to construct for each
piece of equipment or for an entire facility, depending on district
procedures. The authority to construct specifies facility design, conditions
for operation, and emission limits. This permit allows the applicant to
construct the facility. In some cases, the district authorizes the authority
to construct to also serve as a temporary permit to operate, allowing the
applicant to conduct operational shakedown of equipment for a limited period
of time.
5. Issuance of a Permit to Operate
After the project is constructed, the district usually conducts an
inspection to ensure that it complies with permit conditions regarding
facility design. Source tests may also be required to demonstrate compliance
with emission limits. Once the district is satisfied that the project can
operate in compliance with its regulations, a permit to operate is issued.
The Health and Safety Code requires annual review of all permits to determine
that permit conditions are adequate to ensure compliance with, and the
enforceability of, district rules and regulations applicable to the equipment.
In addition, the project must demonstrate compliance with the permit
conditions for the life of the project. This is often achieved by periodic or
continuous testing of emissions, or recording of operating parameters.
Districts also make periodic inspections.
The existing process of issuing a permit to operate is being modified for
major sources, as required by regulations developed under Title V of the
Federal Clean Air Act amendments. The intent is to improve the federal
enforceability of operating permits. The regulations specify the minimum
requirements for operating permit programs, including standardized application
forms for permits to operate and criteria and timelines for review. In
addition, the regulations allow a permit to operate to be valid for up to five
years, as long as there are provisions for reopening the permit when necessary
(e.g., if upon annual review permit terms need to be added or amended).
B. PERMIT STREAMLINING
The permit processing system described above was first established when
districts permitted primarily large sources of air pollution. In more
populated areas of the state, this was not sufficient to attain and maintain
the air quality standards, so smaller sources of air pollution are now
permitted and controlled. This has increased the workload at those districts
and, in some cases, slowed the issuance of permit decisions. A number of
districts, particularly larger districts that process greater numbers of
permit applications, have investigated ways to improve the existing system, so
applications can be processed more quickly, without having a detrimental
effect on air quality. As a result, several districts have implemented
changes, some minor and some fairly major, to various aspects of their
permitting process. For the most part, these streamlining activities at the
districts have been developed independently, yet they often address similar
permitting concerns. Most streamlining measures implemented or under
consideration by the districts are designed to do one or more of the
following:
1) improve the completeness of the applications received;
2) expedite the districts' review once applications are complete;
and
3) improve communication with applicants.
The result of these efforts is that permits, particularly for smaller
sources, are issued more quickly. In some districts, permits for small,
commonly used equipment can be obtained in less than an hour, if they meet
specified conditions. Besides benefitting those applicants, district workload
is reduced.
In addition to individual district efforts to improve their permitting
process, the state legislature last year enacted a number of statutes that
require or allow districts to adopt specific programs to streamline their
permitting process. In particular, the Air Pollution Permit Streamlining Act,
which went into effect in September 1992, requires the largest districts to
establish expedited permitting processes containing specific elements
described in Chapter III.
III.
AIR POLLUTION PERMIT STREAMLINING ACT (AB 2781)
This chapter describes the requirements of the Air Pollution Permit
Streamlining Act and district activities that are consistent with the intent
of the Act.
A. GENERAL REQUIREMENTS
The Air Pollution Permit Streamlining Act (Health and Safety Code section
42320-42323; AB 2781, Sher), which went into effect in September 1992,
requires districts to review their permit programs and to institute new,
efficient procedures, if they haven't done so already. The purpose is to
assist business in complying with air quality laws in an expedited fashion,
without reducing protection of public health and the environment. The Act is
included in Appendix C.
The Act requires districts with populations of 250,000 or more people to
adopt, by regulation, an expedited permit system which includes elements
specified in the statute. There are currently ten districts with populations
of 250,000 or more people: Bay Area AQMD, Mojave Desert AQMD, Monterey Bay
Unified APCD, Sacramento Metropolitan AQMD, San Diego County APCD, San Joaquin
Valley Unified APCD, Santa Barbara County APCD, South Coast AQMD, Ventura
County APCD, and the Yolo-Solano AQMD.
The ARB is required to assist districts with populations under 1,000,000
people in developing regulations implementing these requirements. The
districts that ARB is required to assist includes Mojave Desert AQMD, Monterey
Bay Unified APCD, Santa Barbara County APCD, Ventura County APCD, and Yolo-
Solano AQMD. In addition to this required assistance, the ARB will assist
other districts in developing measures to streamline permitting.
Some of the districts already have programs or plan to have programs that
are consistent with the requirements of the Streamlining Act. The specific
streamlining elements required under the Act are described below, along with a
description of related district activities. It should be noted that to comply
with the Act, these measures must be adopted by the districts as regulations.
B. PRECERTIFICATION OF COMMONLY USED EQUIPMENT
1. Requirement to precertify commonly used equipment
The Streamlining Act requires affected districts to establish "a
precertification program for equipment which is mass-produced and operated by
numerous sources under the same or similar conditions." The goal of this
requirement is to allow applicants to obtain permits for commonly used
equipment as quickly as possible and with minimal paperwork. For districts,
establishing such a program could require substantial resources, but the time
for issuing individual permits would be reduced.
Participants at the CAPCOA/ARB public workshop on permit streamlining
commented that precertification should be a high priority program.
Suggestions were made that more equipment should be precertified, that more
districts should precertify equipment, and that there should be more
uniformity between districts, possibly through a state-wide precertification
program. See Chapter V for additional comments.
2. District activities to precertify commonly used equipment
Currently, one district has a formalized precertification program. The
South Coast AQMD certifies simple, commonly used off-the-shelf equipment under
their Equipment Certification Program (see Appendix D). The program's goals
are to expedite permit processing without decreasing the level of permit
evaluation, to reduce permit process fees, to ensure use of best available
control technology (BACT), and to provide buyers with conditional operating
parameters prior to obtaining permits.
The Equipment Certification Program allows equipment manufacturers to
have their equipment certified voluntarily by the district to assure
compliance with district rules and regulations, including BACT, offset
requirements, and toxic rules. To certify equipment, the district's
evaluation follows the same procedure as a typical evaluation for a permit to
construct (the South Coast AQMD uses the term "permit to construct" instead of
"authority to construct"). Once the evaluation is completed and results are
satisfactory, the district transfers the equipment information to the
district's computer assisted permit processing system (see Section IV.C.5) and
issues a "certified equipment permit" for that make and model of equipment.
The permit is good for one year, unless an extension is granted by the
district. This permit is not an actual permit to construct, since buyers of
the equipment must still apply for permits under the district's "Registration
Program." The benefit for the buyer is receipt of the permits under a very
expedited schedule.
The buyer of certified equipment receives with the equipment a model-
specific end-user package, including an application form and the required
permit conditions. After submitting the application form to the district, the
applicant receives the permit to construct and permit to operate within three
working days, at a reduced cost. In receiving the permits, the applicant
agrees to use the certified equipment only within the parameters specified in
the permit (if an applicant wishes to have different permit conditions, the
normal permit process is followed). Equipment certified under this program is
subject to the district's typical compliance program, including, where
appropriate, source testing, emission quantification, recordkeeping, toxic
reviews and compliance testing.
The South Coast AQMD currently has certified equipment in the following
categories: emergency internal combustion engines, abrasive blasting
equipment, dry cleaning equipment, charbroilers, soil remediation equipment,
small boilers, and automotive spray booths. Other types of equipment may be
certified in the future.
3. Related district activities to precertify commonly used equipment
Some other districts also offer expedited permitting for commonly used
equipment operated under similar conditions. In those districts,
manufacturers do not apply for inclusion in the program, rather inclusion is
based on the district's determination that the equipment is suitable for
quick, standardized permitting. Equipment information, engineering
evaluations, and standard permit conditions are programmed into the computer,
so when an application is submitted, only the project-specific information
needs to be input. District staff then checks the evaluation and conditions,
and in many cases, issues a permit over the counter. To qualify for this very
quick permitting, the equipment must meet certain criteria, for example, it
can not be located within 1000 feet of a school, trigger toxics review, or
need permit conditions other than the standard conditions. It should be noted
that expedited permitting does not affect district requirements for compliance
inspections and renewal of operating permits.
Examples of expedited permitting for commonly used equipment include San
Joaquin Valley Unified APCD's program to issue an authority to construct over
the counter for service stations, dry cleaners and oil field sump
replacements. Offsets are not required for these types of sources in this
district. The authority to construct is issued in about 20 minutes. If the
applicant chooses not to wait while the permit is prepared, it can be sent by
mail within 2 weeks.
The San Diego County APCD has prepared a list of certified dry cleaning
equipment that can be permitted over the counter within an hour. When
installation is complete, the business notifies the district and receives
permission for a 30-day shake down. The district inspects the facility during
the shake down period and issues the permit to operate. A separate
application for the permit to operate is not required.
The San Diego APCD is also pre-approving small cold solvent degreasers
that recently came under their permitting rules. The manufacturer of the most
common degreasers provided the district with information on the equipment,
which the district approved. Users of those degreasers receive permits under
an expedited schedule.
Other districts currently expedite, or plan to expedite, permitting of
certain commonly used equipment. The Kern County APCD precertifies
IC engines. Computer automated permitting of gasoline stations and dry
cleaning equipment allows Ventura County APCD to permit these common sources
in no more than 30 days, and typically within 7 to 14 days after receiving a
complete application. The Sacramento Metropolitan AQMD is planning to
precertify dry cleaning, vapor recovery and, possibly, sand blasting
equipment. The Bay Area AQMD is currently developing an automated permitting
program for quickly approving or denying a combined authority to construct and
permit to operate for sterilizers, autobody shops, solvent degreasers,
gasoline dispensing facilities, and dry cleaners. A program to precertify
commonly used equipment is also planned in Santa Barbara County APCD.
C. CONSOLIDATED FACILITY PERMITTING
1. Requirement to consolidate facility permitting
The Air Pollution Permit Streamlining Act requires districts with 250,000
people or more to establish a consolidated permitting process for any source
that requires more than one permit. This section of the Act specifies that
sources (in this context, "sources" is understood to mean "facilities") must
be permitted on a facility or project basis, there must be a single point of
contact for the permit applicant, and a source must be reviewed and permitted
on a single consolidated schedule.
This requirement is intended to alleviate problems that can result when
very large districts have several staff processing applications for different
pieces of equipment that are part of the same complex facility. When the
applications are processed separately, the permit decisions can be made at
different times, and it can be difficult to keep track of the status of each
application. This section of the Act would benefit applicants of complex
facilities by giving them more certainty on the timeline for permitting the
entire facility and by giving them a single contact at the district where they
could find out how applications for the entire project are progressing.
Participants at the CAPCOA/ARB public workshop on permit streamlining
commented that the ability to track applications is critical to business. See
Chapter V.
2. District activities to consolidate facility permitting
Districts currently have different approaches to permitting complex
projects. About half of all districts issue a single permit for an entire
facility, generally with conditions and emissions limitations for specific
pieces of equipment. Other districts issue separate permits for each emission
unit, sometimes on a single schedule.
The need for a single point of contact is not a concern in smaller
districts where there are few permitting engineers. In medium and larger
districts, applicants are typically given the name of the permitting engineer
who serves as the primary contact. A reorganization at the South Coast AQMD
consolidated all permitting, enforcement and rules staff by industry type that
they serve. Applications for complex facilities are now handled within the
industry group, eliminating previous problems with multiple contacts. See
Sections IV.B.1 and IV.C.6 for more information on efforts to assist
applicants in tracking progress of applications.
D. EXPEDITED PERMITTING FOR MINOR, MODERATE AND MAJOR SOURCES
1. Requirement to expedite permitting schedule
The Air Pollution Permit Streamlining Act requires districts with
populations of 250,000 people or more to establish an expedited permit review
schedule, based upon the types and amounts of pollution emitted from sources.
Each affected district is required to classify sources within its jurisdiction
as a minor, moderate or major source of air pollution, and to establish a
permit action schedule for each classification for approving or disapproving a
permit application.
Most district rules currently have only one schedule for processing
applications, regardless of the size of the project. In almost all cases, the
rules specify that the district must issue a decision to approve or deny an
application for an authority to construct within 180 days from the time an
application is deemed complete or the EIR is certified, if CEQA applies. If
the district is the lead agency under CEQA, it has one year to issue its
decision on the authority to construct application (see Section II.A.3).
Although complex projects may need the full 180 days for review, simpler
projects, which generally have lower emission rates, can often be processed in
less time. The length of time it takes to issue permit decisions for simpler
projects can be more of a result of permit backlog than actual processing
time. This section of the Act puts higher priority on smaller projects,
requiring districts to handle these projects separately, rather than on a
"first come, first served" basis with the larger projects.
At the CAPCOA/ARB public workshop on permit streamlining, there was
support for the concept of tiered permitting. Comments were made that the
tiers should be based on the complexity of the project, not on emission rates.
See Chapter V for additional comments on tiered permitting and other expedited
permitting.
2. District activities to expedite permitting schedule
a. Expedited schedules for sources with low emission rates
In 1992, the South Coast AQMD adopted a practice of processing
applications for small sources within 7 days, medium sources within 30 days,
and large sources within 180 days of the application being deemed complete.
The source categories are based on criteria including: emission level of
criteria air pollutants, public noticing requirements, toxics risk, CEQA
requirements, and modeling and offsets requirements. Since the district
began the program, one third of all applications have qualified for expedited
permitting; about 24 percent meet the criteria for 7 day permitting and 9
percent for 30 day permitting. More detailed information is contained in the
district document "7/30/180 Day Permit Application Pre-Screening Guidelines"
(see Appendix E). The district is able to meet these short timelines by using
computer automated processing of applications (see Section IV.C.5).
The Santa Barbara County APCD is also proposing emissions-based schedules
for small, medium and large pollution sources. Permits for small sources with
relatively little air quality impact will be processed more rapidly than
projects that carry more potential to affect air quality. See Appendix S for
Santa Barbara County APCD's proposed program to streamline permitting.
Other districts have or are considering expedited permitting for some
types of commonly used equipment, which have low emission rates. As described
in Section III.B.3, several districts issue permits for certain low-emitting
equipment under an expedited schedule, in some cases within an hour. The
Yolo-Solano APCD issues permit decisions for gasoline dispensing facilities,
dry cleaners and paint booths within 30 days of receiving a complete
application. The Sacramento Metropolitan AQMD permits gasoline dispensing
facilities three days after receiving a complete application. Minor and
moderate sources are permitted by the Modoc County APCD within 30 days, and
major sources within 60 days of receiving all necessary information.
Permitting in these districts achieves the goal of quickly permitting smaller
sources while maintaining more lengthy review times necessary for larger, more
complex sources.
b. Shorter overall review time
In addition to expedited permitting for commonly used equipment with low
emission rates, several districts have policies or rules requiring a permit
decision on an authority to construct in less than 180 days. The Glenn County
APCD for example, has a policy of issuing permit decisions within 30 days of
receiving a complete application. This is extended with the applicant's
consent, when necessary.
The Bay Area AQMD rules require a determination on an application for an
authority to construct for a new or modified source within 60 days of it being
deemed complete. This shortened review time does not apply, however, to
applications for sources near school boundaries (within 1,000 feet) or those
required to meet the provisions for New Source Review. Furthermore, if the
review and approval of a final EIR or Negative Declaration prepared as part
of the application exceeds the 60 day period, the district must make a
determination on the application within 30 days of review or approval.
c. Expedited permitting on request
In addition to the shorter review times described in Sections III.D.2.(a)
and (b), a few districts will expedite the processing of applications on
request. The applicant must demonstrate a reasonable need, and in some
districts, pay an extra fee for this service. Districts that offer this kind
of expedited review include the Santa Barbara County APCD, the San Diego
County APCD, the Kern County APCD, and the Sacramento Metropolitan AQMD. The
Bay Area AQMD is considering offering expedited review on request.
Some participants at the CAPCOA/ARB public workshop on permit
streamlining supported the idea of paying increased fees to have expedited
evaluation of certain permit applications, if it would not slow the processing
of other applications. The extra fee could be used to hire additional staff
to handle these expedited applications. It was suggested that a very large
premium be charged to discourage applicants from requesting this kind of
expedited permitting for all applications. See Chapter V for additional
workshop comments.
E. TRAINING AND CERTIFICATION PROGRAM
1. Requirement for training and certification program
Another requirement of the Air Pollution Permit Streamlining Act is for
districts to establish "a training and certification program for the private
sector personnel, in order to establish a pool of professionals who can
certify businesses as being in compliance with district rules and
regulations." This requirement of the Act does not specify the elements of a
training program, except that it must include a compliance element. Rather,
the Act allows districts to establish programs best suited to the individual
district's needs. For example, training programs could include elements to
train private sector personnel to prepare complete applications, to conduct
engineering evaluations that the district typically conducts, or to inspect
operating facilities for compliance with rules and regulations. Most affected
districts appear to be considering training consultants to prepare more
complete applications.
The intent of this section of the Streamlining Act is to expedite
permitting by reducing the workload at the district. If certified
professionals conduct engineering evaluations for some sources, district staff
would only need to check the work, rather than perform the evaluation.
Inspections by certified professionals would need to be periodically checked,
but staff would be saved from making each inspection. Training certified
professionals to prepare applications would likely result in applications
being more complete when they are first submitted to the district. Since
districts have identified incomplete applications as one of the main areas of
delay in processing permits, having complete applications submitted should
expedite the permit decision. See Section IV.A for other district efforts to
improve the completeness of applications.
2. Other training and certification options
Health and Safety Code section 42300.2 allows districts to establish a
program to certify private environmental professionals to prepare permit
applications. If such a program is established, it must contain specific
requirements which are described in detail in Appendix C and summarized below:
1) certification of professionals who meet district established
qualifications,
2) expedited review by district staff of permit applications
prepared by certified professionals,
3) an audit program to determine whether district requirements for
the preparation of applications have been followed, and
4) decertification of certified professionals under specified
conditions.
3. District activities related to training and certification
The South Coast AQMD has established and is now operating a voluntary
program to train professionals to prepare accurate and complete permit
applications. Persons who elect to enroll in the program are required, for a
fee, to complete three days of training on all aspects of permit applications,
as well as to pass an exam. Successful completion earns the applicant the
designation as a "certified permitting professional." Certified permitting
professionals prepare applications containing all statements, calculations,
and evaluations necessary to determine whether the equipment can be permitted
in compliance with district rules and regulations. The professionals are
given some access to the district's database resources to assist in preparing
this information. District staff can issue permit decisions for applications
prepared by certified permitting professionals in less time, since they need
only review the application and not perform the primary evaluation. See
Appendix F for additional information on the training program at the South
Coast AQMD.
Other districts, such as the San Diego County APCD, are looking at air
quality training programs conducted by the University of California (U.C.)
Extension as a means of satisfying this requirement of the Air Pollution.
Permit Streamlining Act. All campuses of the U.C. Extension offer courses on
air quality management, and some have certificate programs that include a full
curriculum of courses on air pollution (see Appendix G). The programs at each
campus are independent, but most campuses offer courses on air quality
permitting, air pollution laws and regulations, fundamentals of air pollution,
air pollution control systems and strategies, and principles of environmental
toxicology. Several campuses of the U.C. Extension have indicated an interest
in developing a regional or statewide training and certification program
designed to meet the requirements of the Air Pollution Permit Streamlining
Act.
The Ventura County APCD is considering using the U.C. Extension courses
on Air Quality Permitting as optional background training for consultants
interested in receiving district certification. In addition, the district
would administer a mandatory one-day course specific to the district's
permitting program. Consultants would need to pass a district exam before
being certified.
The San Joaquin Valley Unified APCD is exploring the establishment of a
program to train consultants to do engineering evaluations that are currently
done by district engineering staff. The district would still check the
evaluations, but time would be saved by just checking, rather than actually
performing the evaluation.
Air pollution training courses are also offered by the Air Resources
Board Compliance Division through its Uniform Air Quality Training Program.
This program was established to provide statewide consistency in inspection
procedures and a basic education foundation for air pollution control
professionals. While not specifically intended to meet the training and
certification requirement of the Air Pollution Permit Streamlining Act,
courses offered by the ARB could assist in training private environmental
professionals. Courses offered by the ARB Compliance Division are described
in Appendix H.
F. STANDARDIZED APPLICATION FORMS
1. Requirement for standardized application forms
The Air Pollution Permit Streamlining Act also requires the affected
districts to develop standardized permit application forms that are written in
clear and understandable language and provide applicants with adequate
information to complete and return the forms.
Standardized application forms were considered by participants at the
CAPCOA/ARB public workshop to be a high priority for improving permitting.
Comments were made that forms specific to common types of equipment make it
easier for applicants to provide all the information necessary for an
application to be deemed complete. Statewide standardized forms were also
strongly recommended. See Chapter V for a complete list of workshop comments.
2. District activities to standardize application forms
Districts, for the most part, have their own application forms that are
used for applying for permits. The purpose of application forms is to obtain
from the applicant all the information necessary to determine if the proposed
project will meet district rules and regulations. Since permitting rules vary
by district, due in part to attainment status, necessary information can vary.
Applications typically request information regarding the applicant, the
project location, equipment, fuel or materials usage, emissions, control
technology, and mitigation, as applicable.
As discussed in Section IV.A, incomplete applications are a major factor
in delaying the processing and permitting of sources. To improve the
completeness of applications, many districts have revised their forms to make
them easier to understand. To further clarify what information is needed,
some districts have developed separate forms for common types of sources.
These sources typically include gasoline dispensing facilities, fuel
combustion, solvent sources, hot mix asphalt plants, abrasive blasting, and
spray booths. The autobody painting permit application form for Ventura
County APCD further assists applicants by providing expanded explanations
combining equipment information, emission information, and rules compliance
information. Districts with one or more industry-specific application forms
include, but are not limited to the following: Bay Area AQMD, Feather River
AQMD, Mendocino County AQMD, Monterey Bay Unified APCD, Sacramento
Metropolitan AQMD, Mojave Desert AQMD, San Diego County APCD, San Joaquin
Valley Unified APCD, San Luis Obispo County APCD, Santa Barbara County APCD,
South Coast AQMD, and Ventura County APCD. Application forms from these and
other districts have been compiled and are available from ARB.
It should be noted that Title V of the Federal Clean Air Act amendments
require districts to use standard application forms for permits to operate for
major sources.
G. COMBINED AUTHORITY TO CONSTRUCT AND PERMIT TO OPERATE
1. Requirement to combine authority to construct and permit to operate
The Air Pollution Permit Streamlining Act requires affected districts to
consolidate the authority to construct and the permit to operate into a single
permit process, to the extent that the district determines it will not
adversely affect the public health and safety or the environment. The intent
is to reduce processing time and paperwork for stationary sources by requiring
only one permit instead of two. Districts should not consolidate permits,
however, if it reduces protection of air quality.
Health and Safety Code section 42300.1 requires districts that issue
consolidated permits for construction and operation to establish
postconstruction enforcement procedures adequate to ensure that sources are
built and operated as specified in the permit (see Appendix C).
2. District activities to combine authority to construct and permit to
operate
Several districts currently issue combined permits authorizing
construction and operation of certain small sources. Those sources typically
do not require extensive post-construction inspection or emissions testing to
ensure compliance with permit conditions. Combining permits usually requires
districts to modify their fee schedules for this process, since fees would no
longer be collected separately for the two permits.
The San Diego County APCD issues a combined authority to construct and
permit to operate for two common small sources, dry cleaners and small
degreasers. For dry cleaners, the district issues a combined over-the-counter
permit for equipment the district has certified. An inspection is done at the
time of start-up and at two year intervals thereafter. For small degreasers,
a permit is issued if the applicant verifies that the equipment will meet the
district degreaser rule. The district is considering issuing combined permits
for simple routine equipment, such as abrasive blasting equipment, rock
drills, and tar kettles, that are found to be operating without a permit to
operate. In addition to expediting permitting, the combined permit process in
the San Diego County APCD is intended to reduce district fees.
The Yolo-Solano APCD and the Bay Area AQMD currently issue combined
permits for soil remediation projects, which are typically of short duration.
The Bay Area AQMD is also planning to issue combined permits for sources that
will be able to get over-the-counter permits (see Section III.B.3),
specifically sterilizers, autobody shops, solvent degreasers, gasoline
dispensing facilities, and dry cleaners.
The South Coast AQMD routinely issues a single permit for equipment that
does not require a source test and has minimal toxic emissions, such as
charbroilers, dry cleaning equipment, small boilers, small spray booths, small
degreasers, and small IC engines.
The Santa Barbara County APCD is considering developing a combined permit
process for various types of minor and moderate sources where it would not
have a detrimental effect on air quality. Source categories would be
considered for this process if they do not need emissions testing or a
rigorous inspection. Unlike other districts that issue one document that
serves as both the authority to construct and permit to operate, Santa Barbara
County APCD is looking into issuing an authority to construct, then when
compliance has been demonstrated, putting a sticker on that document that
converts it into a permit to operate. Another option under review is to issue
a separate permit to operate, but not require the applicant to file a second
application.
H. APPEALS PROCESS
1. Requirement for appeals process
The Streamlining Act requires affected districts to adopt an appeals
process for applicants that have not received a decision on their application
within the time period established for minor, moderate and major sources (see
Section III.D). The appeals process would allow the applicant, after
notifying the district, to request the district board to set a date by which
the permit will be acted on.
2. District activities related to appeals process
Under existing rules, most districts have a provision stating that if a
decision is not made on an application for an authority to construct within
180 days of being deemed complete, the application is automatically approved
or, in some districts, denied. Since the three tiered expedited permitting
required under section 42322(a)(3) has not yet been adopted into any district
rules, districts have not developed appeals processes for failure to meet
those schedules.
I. SMALL BUSINESS ASSISTANCE PROGRAM
1. Requirement for a small business assistance program
Section 42323 requires districts with 250,000 or more people to
establish a small business assistance program for small business stationary
sources located within the district's jurisdiction. The program must include
several elements, including standard application forms and consolidated
authority to construct and permit to operate, which duplicate requirements of
42322. The small business assistance program must also include: expedited
variance procedures for small businesses and technical assistance for
applicants on the processing of variances; a designated person or office
within the district to serve as a point of initial access and accessibility to
the district for small business persons; and surcharges on permit fees levied
on sources regulated by the district, to be used for the establishment of a
small business economic assistance program, if approved by the district board
at a duly noticed public hearing.
b. District activities related to small business assistance programs
As described in Section IV.F.7, several districts, as well as the ARB,
have or plan to have small business assistance programs. These programs
provide assistance to small businesses in obtaining permits and in operating
in compliance with district rules and regulations. These programs also meet
the requirement that districts have a designated person or office within the
district to serve as a point of initial access and accessibility for small
business persons. District activities related to standardized application
forms and consolidated authority to construct and permit to operate are
discussed in Sections III.F and III.G, respectively. A joint CAPCOA/ARB
effort is planned to simplify and expedite the variance procedures for small
businesses. For example, this effort is expected to assist dry cleaners,
which are required to meet the new control measure for perchloroethylene, with
understanding and utilizing variance procedures.
IV.
OTHER STREAMLINING EFFORTS
In addition to the measures described in Chapter III on the Air Pollution
Permit Streamlining Act, districts in California currently implement, or are
planning to implement, a number of other measures that serve to expedite the
air permitting process. The district efforts described in this chapter are
organized by the type of permitting issue they address, specifically:
improving the completeness of applications, expediting the completeness
review, increasing the permit processing efficiency, reducing review time,
reducing the number of permits processed, and improving communication with
business. Other topics, such as alternative approaches to fees, rule
revisions, and portable equipment, are also included.
A. ASSIST APPLICANTS IN SUBMITTING COMPLETE APPLICATIONS
Districts have identified incomplete applications for authority to
construct as a major cause of delay in the permitting process. When
applications do not contain all the information needed for the district's
evaluation, district staff must request additional information, wait for the
response, and then, once the response is sufficient, begin review. To reduce
this delay in permitting, districts are using several approaches to ensure
that applications are as complete as possible when they are first submitted to
the district. These approaches are based on good communication with
applicants.
At the CAPCOA/ARB public workshop on permit streamlining, participants
recognized the need for applications to be complete when submitted. They
strongly supported the use of pre-application meetings (see below) and
improved application forms (see Section III.F). Workshop comments are listed
in Chapter V.
1. Pre-application meetings
In small districts, district staff often meet with prospective applicants
before the application for an authority to construct is filed. They explain
the district's permitting process and the information needed in the
application, and where appropriate, BACT and other permitting requirements.
In Placer County APCD, district staff use pre-application meetings to obtain
information about a facility so they can develop a facility-specific list of
information needed in the application. This type of personal attention has
long been the practice in small districts that process few applications.
Recently, larger districts, including Monterey Bay Unified APCD, Ventura
County APCD, and San Joaquin Valley Unified APCD, are also encouraging pre-
application meetings with prospective applicants. The extra time involved in
these meetings is more than made up in the reduced time needed to process an
application that is complete when submitted.
All districts, regardless of whether they hold pre-application meetings,
are willing to assist applicants in completing permit application forms. This
is particularly helpful for small businesses that are not familiar with the
district's permitting process.
2. Pre-application forms
A few districts provide applicants with pre-application forms to be
filled out and brought to pre-application meetings. The forms used by the
Ventura County APCD consist of basic questions that include location of
facility, type of product(s) manufactured or services provided, and type of
equipment used. An area map and site plan are also requested. This
information makes it easier for district staff to help the applicant at the
pre-application meeting. The Ventura County APCD's pre-application forms are
contained in Appendix I.
3. Training on permit process
In addition to the training and certification of consultants described in
Section III.E, several districts provide training to business on permitting or
compliance. For example, the Ventura County APCD has held one-day workshops
for consultants and small business on the district's permit process. Smaller
districts typically don't offer formal training, but they do provide
information to businesses on the permit process during pre-application
meetings. The more familiar applicants are with the permit process, the more
likely they are to understand what is needed in the application for the
district to conduct its review.
4. Alternative means of submitting applications
All districts accept applications submitted in person or by mail. In
addition, applications can be submitted to most districts by alternative
methods, such as FAX, telephone, or computer modem. Eighteen districts,
primarily small and medium sized districts, accept applications by FAX, and
others are planning to use this approach in the future. The benefit in using
FAX is to eliminate the time lost in mailing the document.
Applications can be sent by computer modem to the Kern County APCD,
Imperial County APCD, Glenn County APCD and Northern Sierra AQMD. The
San Joaquin Valley Unified APCD is planning to allow applications for some
types of sources to be submitted on magnetic media. These methods of
submittal save time by allowing the district to transfer data to the
engineering evaluation or the permit without re-entering the data on the
computer. As stated in Chapter V, workshop participants would like to see
districts expand their use of computers for submitting applications and
compliance data.
B. APPLICATIONS: ACKNOWLEDGE RECEIPT AND EXPEDITE REVIEW
As stated in Section II.A.2, once the application for an authority to
construct is submitted, the district has 30 days to determine whether the
application is complete. During this time, the applicant may not know who at
the district to call with questions or whether there are major pieces of
information missing from the applications. To help keep the applicant
informed, and to minimize the delays associated with obtaining any additional
information, some districts are implementing the practices described below.
Participants at the CAPCOA/ARB public workshop on permit streamlining
encouraged more districts to adopt these practices; see Chapter V.
1. Acknowledge receipt of applications and identify district contact
Several districts acknowledge receipt of applications before the end of
the 30 day completeness review. At the Amador County APCD, for example,
applications are acknowledged within one day. Several other districts notify
applicants within a week or 10 days that their application has been received.
Some districts that deem applications complete in significantly less than the
required 30 days do not acknowledge receipt of applications, since this extra
step is unnecessary and takes time away from the completeness review.
Districts that acknowledge receipt of applications also use this
opportunity to provide applicants with the application number and the name of
the permitting engineer who serves as the primary contact. This practice
makes it easier for applicant to track the progress of applications in the
permit process. If form letters are used to acknowledge receipt of
applications and identify the district contact, little staff time is required
for this measure.
2. Immediate screening of applications
Due to workload, district staff are not always able to begin their
review of an application immediately after it is submitted. Since
applications are sometimes submitted with substantial pieces of information
missing, some districts have adopted a practice of quickly screening
applications when they are first submitted. District staff, in some cases
non-engineering staff, check to make sure that the application is filled out
completely and that proper documents, such as a risk assessment, are filed
with the application. This screening does not replace the districts'
completeness review or the districts' ability to request further information,
but it saves time by notifying applicants as soon as possible that major
pieces of information are missing from their applications.
3. Applications deemed complete/incomplete in less than 30 days
A few districts are able to deem applications complete or incomplete in
much less than the required 30 days. For example, Colusa County APCD and Kern
County APCD generally make their completeness determinations in seven days.
Shortening this first step of the process reduces the overall permitting time.
4. Standard completeness letters and information sheets on common
application problems
After reviewing an application for completeness, district staff notifies
the applicant that the application is complete, or that it is incomplete and
what information is missing. To reduce staff time spent preparing letters,
some districts have developed standard letters that need only the applicant's
name and project description added. For incomplete applications, the Ventura
County APCD attaches a checklist describing information commonly missing from
applications. This district is also in the process of developing information
sheets on common requirements. At this time, information sheets have been
prepared for emission offset requirements, health risk assessment
requirements, and BACT requirements for wood products coating (see Appendix
J). These efforts reduce the staff time required for individual projects,
although the initial preparation of the standard materials takes time.
Applicants benefit by having carefully prepared information on application
requirements, and by receiving a somewhat faster permit review.
C. INCREASE PERMIT PROCESSING EFFICIENCY
After an application for an authority to construct is deemed complete,
the district evaluates the proposed facility to determine whether it complies
with all district rules and regulations. Depending on the type and size of
the facility, this evaluation can include estimating emissions, determining
BACT, conducting an air quality analysis, evaluating a health risk assessment,
and finally, determining design and operation conditions that should be
contained in the permit. Each step of the evaluation takes time and
contributes to the overall length of the permitting process.
Many districts have developed standard approaches for each step of the
evaluation, particularly for common types of sources. For example, districts
have developed standard evaluation policies, BACT, and permit conditions. In
some cases, computers are used to expedite these standard approaches even
further. In addition to expediting the process, these measures ensure more
accurate and uniform evaluation by technical staff.
1. Standard policies and procedures
Most districts have developed standard policies and procedures for
district staff to follow when preparing engineering evaluations. Some
districts have put these policies and procedures in documents that are
available not only to district staff, but also to applicants. The Bay Area
AQMD and South Coast AQMD have published permit processing handbooks
describing the procedures for evaluating applications for authority to
construct and permit to operate for common types of equipment. These
handbooks include information describing the permitting process, application
contents and completeness, regulations, abatement equipment, emission
standards, permit conditions, enforcement procedures and fees for selected
source categories. Source categories contained in the handbooks include dry
cleaning, storage tanks, boilers, gasoline dispensing facilities, and other
sources listed in Appendix K. Other districts, including San Joaquin Valley
Unified AQMD, are planning to develop permit processing handbooks.
In addition to the information that has been developed by local
districts, the ARB Compliance Division has published criteria for assessing
district enforcement and permitting programs (see Appendix L for general
permitting criteria). These criteria can also be useful to districts in
evaluating ways to streamline their permitting process.
At the CAPCOA/ARB public workshop on permit streamlining, participants
commented that the development of standard policies, procedures, and emission
factors that are available to the regulated community should be a high
priority. See Chapter V.
2. BACT tracking activities
As part of stationary source permitting programs, many districts are
required to determine control technology requirements. New Source Review
rules in particular require California districts to determine BACT and lowest
achievable emission rate (LAER). In most cases, these requirements only
differ by name, since most districts use a BACT definition that is almost
identical to the federal definition for LAER. Usually, district rules require
that sources subject to BACT or LAER requirements apply the most stringent
control technology achieved in practice. These control technology decisions
are discretionary and can require a significant effort to make. Much of this
effort is dedicated to investigating the performance of various technologies
used to control emissions from similar units in the same source category of
the proposed permit unit.
Some districts reduce resource requirements for conducting BACT
determinations through standardization of procedures and requirements. If
BACT determinations are made available to the public, they also serve to
inform prospective applicants in advance of filing an application, what
controls are likely to be required on their projects. Knowing what controls
may be required could be useful in deciding whether to go forward with a
project. It would also allow applicants to include a description of those
proposed controls in their application.
The South Coast AQMD and Bay Area AQMD have formal BACT guidelines which
provide standard procedures for conducting determinations. Source categories
have been predefined, and procedures of evaluation and cost effectiveness
calculations are presented in a district guideline document. The procedures
not only require consideration of controls deemed to be achieved in practice,
but also the consideration of alternative basic equipment and alternative
fuels. In addition, consideration must also be given to identify potentially
feasible controls that are more stringent than controls currently achieved in
practice.
The Bay Area AQMD BACT handbook is currently a working draft. The
district has met with industry groups to consider their recommendations. The
handbook is expected to be finalized in the near future and then updated
annually.
The Ventura County APCD and San Joaquin Valley Unified APCD maintain BACT
manuals which are compilations of their most recent BACT requirements for
various source categories. These are dynamic manuals that change to reflect
current BACT requirements.
At a broader level, CAPCOA has a statewide clearinghouse for district
determinations. Determinations are sent in from districts on a voluntary
basis and compiled into an electronic database. This information is sent back
to the districts in quarterly summaries and periodically published in a
compilation document. When needed, the most recent information can be
requested by telephone.
The U.S. Environmental Protection Agency also has a RACT/BACT/LAER
clearinghouse that compiles information sent in from states. Information from
this clearinghouse can be accessed from its electronic database via modem.
3. Standard permit conditions
Most districts have standard permit conditions they use for common types
of sources. In some districts this is achieved by using applicable conditions
from similar permits. The Santa Barbara County APCD, San Joaquin Valley
Unified APCD, San Diego County APCD, Bay Area AQMD, Ventura County APCD, and
South Coast AQMD have compiled standard permit conditions, typically on
computer. Types of sources for which standard permit conditions have been
compiled include: IC engines, boilers, scrubbers, gasoline dispensing,
coating operations, incinerators/after-burners, and degreasers. Standard
permit conditions can be obtained from districts or, in some cases, from ARB.
Standard permit conditions expedite permitting by reducing the time
district staff spends writing permits. Instead of creating new conditions for
each permit, staff need only check to see what additional conditions or
modifications to standard conditions may be necessary. When standard permit
conditions are made available to prospective applicants, they know in advance
of filing an application what conditions they must meet.
4. Specialized staff for various source categories
District permitting staff generally specialize to allow individuals to
become more knowledgeable on certain types of equipment, which results in more
consistent and expedited permitting. In small districts, this may mean that
one individual handles small sources and another handles the more complex
projects. In larger districts, staff are often specialized by the type of
equipment or the type of industry. For example, the Monterey Bay Unified
APCD, Bay Area AQMD, San Joaquin Valley Unified APCD, and Ventura County APCD
have staff that are experts in permitting specific kinds of sources.
The South Coast AQMD has reorganized into industry teams, with all
permitting, enforcement, and rules staff for a given industry working together
on the same team. A permit application for a complex facility is handled
entirely by the industry team, in comparison to the previous practice of
having different sections at the district process different equipment from one
facility. This industry approach was developed to alleviate communication
problems that can happen in a district of this size.
5. Use of computers to expedite the permit process
a. Benefits of using computers
The use of personal computers has made it possible to automate many
district activities, including permit processing. Districts use computers to
implement many of the streamlining measures described in this document,
including: standard permit conditions (Section IV.C.3), quick permitting of
precertified equipment (Section III.B), quick permitting of minor and moderate
sources (Section III.D), standard policies and procedures (IV.C.1), tracking
permitting status and project emissions (IV.C.6), form letters for receipt of
applications and application completeness (IV.B.1 and IV.B.4), and BACT
tracking (IV.C.2).
In the past, all districts handled and processed permits manually. Many
districts continue to do so, but as regulatory thresholds are lowered and more
sources require permits in larger districts, automation has become an
effective tool for expediting and streamlining the air permit process. It
should be noted, however, that it may not be appropriate for districts to use
computers to assist in all aspects of permitting described in this document.
Districts should evaluate the specific procedures that will produce the
greatest benefit for the least cost.
The best candidates for automated permit processing would be the most
numerous and the simplest sources permitted by the district. For example,
districts that permit small sources, such as dry cleaners, spray booths, and
gas stations may be good candidates for automation. For these types of small
sources that have simple types of controls and standard permit conditions, a
simple template or form can be developed. Technicians can quickly fill out
the forms and the permit can be processed efficiently through a computer
system. This approach streamlines the process by freeing up the more
technical staff to work on more difficult project permits. Some districts
have also placed their permit applications on office automation systems. This
allows permit engineers or technicians to concentrate on reviewing the
application instead of having to key in the data.
At the CAPCOA/ARB public workshop on permit streamlining, participants
put high priority on districts expanding the use of computer-based technology
for processing permits, receiving data from applicants, and communicating with
the regulated community. See Chapter V for additional workshop comments.
b. District computer programs
The following is a summary of how some districts have incorporated
automation into their permit processes. These are examples which other
districts can examine to determine whether these approaches might work well
for them.
The South Coast AQMD has developed a computer assisted permit processing
system (CAPPS) which is linked to the district's mainframe computer. This
program is used by the district's permit engineers to process applications for
permits to construct and operate, particularly applications for small and
medium sources that are permitted under an expedited schedule (see Section
III.D). The CAPPS reduces the number of applications processed manually and
provides automatic calculations and computer-generated forms and reports. The
CAPPS is menu driven and user friendly and "walks" the permit engineer through
the permit process.
The Yolo-Solano AQMD uses a personal computer system to expedite their
permit evaluation. Information requested on the district's 41 source-specific
application forms is evaluated using a computer program that has district
rules, emission rates, calculations, and permit conditions. By pre-
programming the computer to do the permit evaluation and print the permit,
there is a 75% saving on staff time required.
The Bay Area AQMD is developing an automated permitting program so that a
technician can process a permit in 30 minutes. This program is being designed
for commonly used sources that have standard controls and permit conditions,
such as sterilizers, autobody shops, solvent degreasers, gasoline dispensing
facilities, and dry cleaners.
The Ventura County APCD has developed new computerized programs to assist
in issuing operating permits for gas stations and dry cleaning facilities.
The district hopes to expand these programs so the authority to construct can
be converted easily to a permit to operate. The Ventura County APCD also has
a computer program that asks permit engineers a series of questions in order
to properly categorize a permit application in terms of BACT, emission
offsets, toxic new source review, notification requirements, and other
requirements.
The San Joaquin Valley Unified APCD has developed a database for logging,
tracking, processing, and issuing all authorities to construct and permits to
operate. However, these permits are handled separately and engineering
evaluations are performed on word processing software. The district's system
enhances the permit process for district permit engineers, which in turn, can
improve consistency and reduce potential delays for project applicants. The
district's system allows its permit engineers to access permit forms and
records via the district's computer network and to issue annual billings. An
important component of this system is that the district's permit engineers can
call up general permit conditions for a variety of source categories (e.g.,
asphalt batch plant) by specified numbers. The specified numbers for the
general permit conditions enables the district to save memory space. Also,
the district uses its database system for tracking increases in permitted
emissions. The district plans to enhance the system in the future to track
and process emission reduction credits.
San Diego County APCD is working on a computer assisted program that will
reduce duplicate data entry using a relational data base, provide standard
rule evaluation based on source type, provide standard permit conditions based
on the source type, perform the emission calculations using source specific
data, perform fee calculations, and print a draft authority to construct. The
project engineer would review the input data and the resulting rule analysis,
emission calculations, fees, and permit conditions. The program will be used
initially to permit simpler sources such as dry cleaners, abrasive blasting
equipment, and degreasers. The system is being developed on mini-mainframe
computer with implementation beginning in fall of 1993.
6. Tracking systems
Districts have instituted tracking systems, typically using computer, to
monitor permitting activity and emissions inventory. In districts that
process large numbers of applications, it can be difficult to keep track of
where each application is in the permitting process and which staff person is
responsible. Many districts use a tracking system to keep track of the date
applications are received, name of the permitting engineer or other contact at
the district, date the letter of completeness or letter of incompleteness is
issued, date the draft permit is issued, and date the final permit is issued.
In some districts, the tracking system is as simple as a logbook; in larger
districts computerized tracking systems are used. Benefits of application
tracking systems include: 1) responding more quickly to applicant questions
on application status; and 2) allowing the district to evaluate how well
timelines are met and where problems occur in the permitting process.
Districts are further helping applicants to follow the progress of their
applications in the permit process by providing applicants with their
application number and with the name of the permitting engineer (see Section
IV.B.1). At the Cal/EPA public workshop, participants stated that the ability
to track their applications was critical. Workshop comments are listed in
Chapter V.
Previous legislation (Health and Safety Code section 40709.5) required
that districts develop and implement a system that identifies and tracks
sources possessing emission credit balances and allows periodic analysis of
increases or decreases in emissions from new or modified sources. These
tracking systems are being used to verify that the district permit programs
are achieving the goals specified by state law.
7. Streamlining Toxics Screening
The requirement to conduct a health risk assessment can sometimes slow
the issuance of air permits. To avoid unnecessary delays, the Monterey Bay
Unified APCD has developed a method to screen projects that do not pose
unacceptable risk and therefore do not need a comprehensive health risk
assessment. The method is currently specific to contaminated soil and water
aeration projects. Using project-specific analysis of the soil, estimated
soil volume, and the distance from the source to the property line, the
district is able to use previously run dispersion models to determine if the
project would result in a risk below ten in one million. If so, the permit
for the soil aeration project can be issued on an expedited basis.
8. Evaluation of unpermitted sources by inspectors
While inspecting existing sources, district staff occasionally discover
unpermitted sources. In addition to being subject to fines, these sources are
required to file for the necessary permits and undergo district inspection
before receiving a permit to operate. To expedite permitting of currently
operating unpermitted sources in San Diego County, the district inspector
provides the business with the necessary application forms at the time the
unpermitted source is discovered. In addition, the district does not require
a second inspection, but relies on the original inspection that discovered the
source.
D. INCREASE EFFICIENCY OF DISTRICT CEQA REVIEW
As stated in Section II.A.3, before the district can issue a decision on
an application for a project which may have a significant effect on the
environment, the project must comply with CEQA. Since the district is often
not the lead agency, it has limited ability to expedite the entire CEQA
process. There are a few district efforts described in this section which
streamline the CEQA process as it affects the district.
1. Designated CEQA staff
Many districts have designated staff conduct evaluations required under
CEQA. At the Bay Area AQMD, for example, CEQA is handled by the planning
division, rather than by permitting staff. This allows planning staff to be
knowledgeable on CEQA and permitting staff to focus on permitting issues.
2. Ministerial CEQA permit process for designated sources
Several districts consider permit decisions for certain types of
facilities to be ministerial, and therefore exempt from CEQA. The Bay Area
AQMD's regulations specifically exempt from the CEQA process permit
applications that the district defines as ministerial. Under the Bay Area
AQMD's regulations, the ministerial exemption is limited to permit
applications for projects that: 1) have no significant environmental impacts
for all environmental media; 2) comply with district, state, and federal air
quality rules, regulations, and laws; and 3) are not unique so district staff
can evaluate them through the district's manual of procedures. Complete
description of criteria for ministerial exemption is contained in Bay Area
AQMD regulations 2-1-311, 2-1-427, and 2-1-428. The district and project
applicants both benefit from this approach by eliminating the time and costs
incurred in complying with the CEQA requirements.
E. REDUCE THE NUMBER OF PERMITS PROCESSED
Some districts process large numbers of permit applications for new and
modified sources. To streamline the permitting process, districts are
considering or implementing ways of reducing the number of applications that
must be processed, without compromising air quality. In addition to the
measures described below, several districts are consolidating the authority to
construct and permit to operate for some sources (see Section III.G).
1. Modify permit exemption list
In 1990, the CAPCOA NSR Task Force developed recommendations for source
categories that could be exempt from district permitting requirements (see
Appendix M). Many districts have incorporated in their rules some or all of
the recommendations. Recently, districts have indicated an interest in
expanding the CAPCOA permit exemption list to include more sources that have
low levels of emissions. The intent would be to reduce the number of small
sources requiring permits, thereby allowing districts to focus their resources
on sources with larger levels of emissions. Depending on how districts use a
revised exemption list, it may also provide some level of consistency between
districts in how they handle very small sources.
2. Registration of small sources
As an alternative to exempting sources with very low emissions, a few
districts, including Santa Barbara County APCD and San Diego County APCD, are
exploring the idea of registration programs for off-the-shelf equipment. The
business would still have to fill out forms and likely pay a fee, but the
process would be much faster than if the source required a permit. Although
this would take more district resources than completely exempting these
sources, it would provide an opportunity for tracking emissions.
3. Portable Equipment
Prior to operating equipment that may emit air pollutants, applicants
must obtain permits from the local districts. For equipment that is moved
from district to district, permits currently must be obtained from each
district where the portable source might operate. To reduce this burden on
businesses that own portable equipment, efforts are underway to develop a
statewide program where portable equipment would require only one air permit.
Establishing a statewide program for portable equipment would also increase
the district's efficiency in processing permits by reducing the number of
permits processed.
San Joaquin Unified APCD has taken the lead to develop proposed
regulations for a program to streamline the permitting of portable equipment.
Several workshops have been held to receive public comment on the proposed
regulation. Any comments received will be considered in the development of
the final draft regulation that will be presented to the CAPCOA Board of
Directors. Once approved by the CAPCOA Board, individual districts will adopt
the regulation.
Under the proposed regulations, district participation in the portable
equipment program would be voluntary. Equipment eligible for the program
would be limited to certain types of equipment that emit less than 10 tons per
year. Applicants would need to obtain permits from only one district, the
district where the owner/operator's headquarters are located. New equipment
would be required to employ BACT and existing equipment would employ best
available retrofit control equipment. The district would provide any
necessary mitigation.
4. Five year term for operating permits
Renewal of operating permits, while not requiring the same resources as
reviewing an application for an authority to construct, contributes to the
overall workload at the districts. To reduce that effort and the associated
paperwork, the San Joaquin Valley Unified APCD has changed the renewal of
operating permits from annual to every five years. The district still does
annual inspections and, if necessary, modifies the permit, and fees are still
charged annually. The benefit is reduced paperwork without affecting
compliance. Five year terms for operating permits are consistent with Title V
requirements in the federal Clean Air Act Amendments (see Section II.A.5).
It should be noted that regardless of the frequency of renewing
permits, districts must still conduct annual permit review in accordance with
Health and Safety Code section 42301(c). This section of the code requires
annual review to determine that permit conditions are adequate to ensure
compliance with, and the enforceability of, district rules and regulations
applicable to the equipment. If the conditions are not consistent, the permit
must be revised to specify the permit conditions in accordance with all
applicable rules and regulations (see Appendix C).
F. IMPROVE COMMUNICATION WITH THE REGULATED COMMUNITY
Many of the previously described changes that districts are making to
improve and expedite the permitting process involve better communication with
the regulated community. For example, pre-application meetings (Section
IV.A.1), training businesses on the permit process (Section IV.A.3),
acknowledging receipt of applications and identifying a single district
contact (Section IV.B.1) help to improve communication between districts and
the regulated community. Other district efforts described in this section
include using brochures and working with economic development corporations to
help businesses understand district rules and regulations, and the air permit
process. Districts are also soliciting suggestions from businesses on
improving the permit process and other districts programs.
Improved communication was stressed as a top priority by participants at
the CAPCOA/ARB public workshop on permit streamlining. Specific
recommendations included: more interactive workshops, pre-workshop meetings
with affected industry, computer bulletin board, and E-mail. In addition,
workshop participants urged districts to adopt a non-adversarial, "customer-
service" attitude. See Chapter V for additional workshop comments.
1. Brochures and other permit assistance materials
All districts provide businesses with permit assistance materials on
request. Some districts have developed brochures as an easy way of informing
applicants of the need for air permits and how the permit process works. In
addition to a description of the main points of a district's permit process,
permit brochures typically contain sections that discuss the following:
reasons why permits are required, who is required to obtain a permit, what are
the different types of permits that may be required, and where to go or who to
contact if more information is needed. The Santa Barbara, Ventura, San
Joaquin Valley Unified, and Monterey Bay Unified Air Pollution Control
Districts are among the districts that have developed brochures that address
the permit process. For examples of these and other brochures please refer to
Appendix N.
In addition to brochures on the permitting process, most districts have,
or are developing, materials on enforcement, emissions testing, or district
policies. Districts also distribute compliance assistance publications
prepared by the ARB Compliance Division (see Appendix N for a list of
available publications). In addition, districts issue advisories to industry
on important topics. While these materials may not necessarily expedite the
issuance of permit decisions, they assist businesses in complying with air
quality rules and regulations, and improve overall relationships between the
districts and businesses.
2. Work with Economic Development Corporations in explaining air
permit process
Some districts are providing permit assistance and informational packages
to businesses through local economic development corporations. Economic
development corporations throughout the state assist businesses in obtaining
loans. However, in San Diego County and San Joaquin Valley, the corporations
are additionally acting as the middleman for the districts to provide permit
assistance to businesses. The San Joaquin Valley Unified APCD staff meet with
businesses to discuss the permit process, information needed on applications,
regulations, and cost effective means of complying with district rules and
regulations. The districts have found that helping businesses through the
economic development corporation has worked well, and often results in
applications being more complete when first submitted.
The South Coast AQMD works with the existing California Business
Environmental Assistance Center (BEAC) in southern California to inform
businesses of the need for air permits, and to provide information on the air
permitting process. Districts will also coordinate with a second BEAC that is
planned for northern California.
3. Client feedback through questionnaires
Questionnaires are used by several districts to obtain applicant feedback
on the permit process and on district compliance inspections. Their use can
achieve two purposes. First, they can provide districts with information that
may be used to improve the permit process or the inspection process. Second,
they can improve communication between the district and businesses.
Questionnaires usually ask a variety of questions such as: were the rules and
permits understandable, was the engineering staff helpful in providing
assistance, and were all the applicant's questions answered fully. On the
questionnaire, space is also provided for the respondent to make comments or
suggestions. Examples of permit processing surveys (questionnaires) can be
found in Appendix O.
4. Industry recommendations for improving the permitting process
CAPCOA has an ongoing program to improve communication with business.
In addition to the CAPCOA/ARB workshop on permit streamlining described in
Chapter V, other workshops have been held to share information and solicit
input from the regulated community on air quality issues, such as permitting
of portable equipment and compliance with Title V requirements. CAPCOA also
meets monthly with industry representatives to discuss permitting issues,
proposed legislation, and other air quality issues.
Several districts have solicited industry recommendations for improving
the permit process. The Ventura County APCD held a workshop in 1992 with
permit holders to obtain their input on permit streamlining. As a result, the
district has instituted several streamlining measures described in this
document. Last year, San Diego County APCD initiated an effort to improve its
overall program, emphasizing input and participation from business. The
district began by sending survey forms to all affected businesses and by
meeting with business groups and associations. In addition, a workshop was
held to solicit comments on where improvements could be made. As a result of
these initial efforts, a working group of district and local industry
representatives was formed to review the permit issuance program in detail and
evaluate ways it could be improved. The working group has held a number of
meetings and developed a specific process for both businesses and the district
to follow that will expedite the permitting process.
5. Hot line
When businesses have questions on air permitting or compliance issues,
they want to be able to call someone at the district who can help them. In
small districts with few staff, calls can be quickly directed to the right
individual. In large districts this can be more of a problem, so several
districts have established hot lines. Some of the hot lines were originally
established to handle compliance questions. However, they can also be used to
help with answering permitting questions. The Bay Area AQMD, Kern County
APCD, Lake County AQMD, Mojave Desert AQMD, Placer County APCD, South Coast
AQMD, and Ventura County APCD currently have hot lines.
6. Multilingual Staff
Many districts currently have multilingual staff who are available to
assist businesses in understanding permitting and compliance requirements.
7. Small Business Assistance Programs
Several of the streamlining measures described in this document,
including pre-application meetings (Section IV.A.1), training on permit
process (Section IV.A.3), and brochures and other permit assistance materials
(IV.F.1), assist small businesses in obtaining permits or in complying with
district rules and regulations. In addition to these measures, several
districts have established or are planning to establish small business
assistance programs. For example, the Sacramento Metropolitan AQMD is
establishing, in cooperation with other county agencies, a Small Business
Assistance Center. Assistance offered by the Center will include help in
filling out permit applications, workshops on self-inspections for regulatory
compliance and pollution prevention, and industry-specific manuals with easy-
to-understand information on all environmental regulations that apply to that
industry in the county. Other districts that have or plan to have small
business assistance programs include the Bay Area AQMD, San Diego County APCD,
San Joaquin Valley Unified APCD, and South Coast AQMD.
In addition, all districts with populations in excess of 250,000 are
required by the Air Pollution Permit Streamlining Act to develop small
business assistance programs. The program must contain specific elements
including expedited variance procedures for small businesses, a designated
person or office at the district to serve as initial contact for small
businesses, and after district board approval, a small business economic
assistance program. See Appendix C for details.
The ARB is currently developing a small business assistance program in
compliance with the federal Clean Air Act Amendments of 1990. The Clean Air
Act Amendments require each state to develop a program to assist small
businesses that must obtain federal operating permits required by Title V of
the Amendments. The state program mandated under the Clean Air Act Amendments
must include three elements: 1) a state Small Business Ombudsperson; 2) a
Compliance Advisory Panel; and 3) an outreach mechanism to provide technical
assistance and to distribute compliance information to small businesses. The
program being developed by the ARB goes beyond the federal mandate by
providing assistance to all businesses operating or wishing to operate in
California. Based on information provided by the business community, there is
a need for general information pamphlets especially geared for the small
business, regulatory assistance manuals written in layperson terms, and a
helpline that would provide assistance or referrals on environmental
questions. The ARB has been coordinating the development of this program with
the districts, other state agencies, chambers of commerce, small business
development centers, trade associations, and businesses. For more
information, see Appendix P.
G. COORDINATE WITH OTHER AGENCIES
Local air districts are responsible for permitting facilities and
ensuring compliance with air quality rules and regulations. Other local,
state, and federal agencies can have other permitting and compliance
responsibilities at the same facilities. The number of agencies that can be
involved at any particular facility can potentially lead to overlapping or
conflicting operating requirements and facilities may be subject to
inspections by several agencies.
To reduce duplication or conflict in permitting and inspections,
districts coordinate with other agencies, particularly other local agencies.
This can reduce district workload in some cases, but more importantly, it
minimizes the burden on businesses.
At the CAPCOA/ARB public workshop on permit streamlining, comments were
made on ways districts could coordinate with other agencies, for example by
developing multimedia application and compliance forms; see Chapter V.
1. Coordinate with city/county agencies issuing building permits
Most districts are working with city and county building and planning
departments to ensure that businesses are aware that they may need air
permits. Government Code section 65850.2 states that building departments can
not issue the final permit of occupancy until air permits have been obtained,
if needed. Therefore, it is to the advantage of both the building departments
and the districts to work together in informing applicants of the possible
need for an air permit.
The Monterey Bay Unified APCD has encouraged cities and counties to
include language in their building permit application forms asking applicants
whether an air permit is required (see Appendix Q). The district's telephone
number and a list of typically exempt sources are included.
The Yolo-Solano APCD has asked city building departments to provide
building applicants with an air pollution survey (see Appendix Q). The survey
is filled out by the applicant and sent to the district together with the
building permit application. The district uses this information to determine
if an air permit may be required.
The Bay Area AQMD works with the building, planning and fire departments
to ensure that applicants know when they may need an air permit. The district
has developed postcards that are filled out by the departments and the
applicants, and sent to the district (see Appendix Q). If the district
determines an air permit is required, the applicant is notified. The district
also provides a fact sheet on the types of sources that need permits and a
brochure about the district (see Appendix N).
2. Coordinate facility inspections with other agencies
Many districts coordinate, or plan to coordinate, facility inspections
with other agencies. Most common is the coordination of inspections of
gasoline dispensing stations with county staff responsible for checking
weights and measures.
3. Coordination on contaminated soil cleanup
Cleanup of contaminated soil involves air districts as well as local
health departments and other agencies. Districts typically coordinate with
the other agencies in these efforts. For example, the Great Basin Unified
APCD coordinates with the local health department on soil remediation projects
to ensure that permit conditions are compatible. The South Coast AQMD
coordinates with the health department on cleanup of superfund hazardous waste
sites.
4. Coordination on underground tanks
The Sacramento Metropolitan AQMD coordinates with the county hazardous
materials staff and city and county fire departments on applications for, and
inspection of, underground tanks at gasoline stations. They have developed a
consolidated application for installing and operating vapor recovery systems
and underground storage tanks for hazardous substances. The district also
coordinates inspections with these agencies.
5. Coordinate with California Energy Commission
All districts coordinate with the California Energy Commission in the
permitting of energy facilities of 50 megawatts or more capacity.
6. Coordination on PM10 Issues
The Great Basin Unified APCD has coordinated with the U.S. Soil
Conservation Service and CalTrans on reducing fugitive dust problems in the
district. The Great Basin Unified APCD has also worked with the town of
Mammoth Lakes in developing and implementing a PM10 State Implementation Plan
for woodsmoke and road dust. The district issues permits for development that
has associated indirect emissions. The town issues permits for woodstoves,
which reduces the workload at the district. The Northern Sonoma County APCD
coordinates with the building departments to ensure that approved woodstoves
are used in new construction.
7. Other Coordination
Districts are also coordinating with other agencies to avoid duplicative
requests. For example, the San Diego County APCD is working with the County
Health Department and Department of Agriculture to explore areas of
coordination in permitting and inspecting businesses.
Some districts coordinate efforts with industry for improving air quality
or assisting business through the permitting process. The Ventura County APCD
works with Southern California Edison and Southern California Gas by
"advertising" the permit assistance programs offered by these utilities to
interested permit applicants.
H. OTHER EFFORTS TO IMPROVE AIR PROGRAMS
There are other changes that districts have made, or are planning to
make, so permitting and compliance requirements are easier for business,
without compromising air quality. These changes are being made to
recordkeeping and reporting requirements and fee payment methods; in addition,
loan guarantee programs are assisting businesses in complying with
environmental regulations.
1. Streamlining recordkeeping and reporting requirements
In response to industry requests, some districts are working to
streamline their recordkeeping and reporting requirements, particularly for
volatile organic compounds. The San Diego County APCD is working with EPA and
ARB to revise the daily recordkeeping requirement for storage of materials
containing volatile organic compounds. The district is also providing sample
recordkeeping forms to businesses to promote consistency and to ensure records
are properly kept.
The Santa Barbara County APCD has developed a proposal for streamlining
recordkeeping requirements; see Appendix S. The proposal includes a number
of elements including:
- surveying records to identify little-used data,
- defining recordkeeping requirements for small, medium and large
- sources and eliminating recordkeeping for very small sources,
- adopting a single recordkeeping rule and revising other rules to
- eliminate unnecessary recordkeeping,
- exploring simplifying approaches,
- making recordkeeping requirements consistent regardless of permit issue date,
- exploring setting emission limits only at regulatory significance levels, and
- exploring control and recordkeeping at the point of sale or distribution.
The South Coast AQMD's program to streamline recordkeeping and reporting
for volatile organic compounds is described in Appendix R. As a first step to
revising the requirements, the district conducted a pilot project for small
and medium sized businesses. The result is a program that allows facilities
to record and report emissions based on usage of broad categories of materials
containing volatile organic compounds, such as solvents, coatings, and
adhesives. The gallon usage is then multiplied by corresponding incremental
emission factors. Alternative approaches for reporting emissions were also
evaluated. Streamlined recordkeeping and reporting requirements have been
incorporated into the draft rules proposed for the Region Clean Air Market
(RECLAIM). In addition, small non-RECLAIM sources may elect to use the
streamlined recordkeeping alternatives.
Comments were made at the CAPCOA/ARB public workshop on permit
streamlining that simplified recordkeeping should be a high priority. See
Chapter V for specific comments.
2. Alternative approaches to fees
To assist businesses in paying permitting fees, some districts have
established, or are considering, small business discounts or payment with
credit cards.
a. Small business permit fee discount
Small businesses are charged reduced permit fees in Glenn County APCD,
Tuolumne County APCD, Bay Area AQMD, Lake County APCD, and South Coast AQMD.
A discount of 50 percent is typically given. The San Diego County APCD allows
small businesses to pay fees over time. Reduced fees do not expedite
permitting, but they do encourage small businesses in those districts.
b. Accept credit cards as payment for permit fees
The Bay Area AQMD began accepting permit fee payments by credit card in
September 1993, and Kern County APCD is considering a similar program.
Allowing payment by credit card is expected to help medium and large
businesses that otherwise may take a long time to issue a check. Since
permits are not issued until fees are paid, this would expedite permitting.
Some businesses may also benefit from the extended payment time of credit card
bills.
3. Loan guarantee programs
The state has instituted the California Loans for Environmental
Assistance Now (CLEAN) program for small businesses. Under CLEAN, eligible
small businesses may apply for loans to assist them in complying with
environmental laws and regulations. Loan activities are conducted by the
California Office of Small Business with the California Pollution Control
Financing Authority making determinations on loan approvals. Loans may be a
minimum of $10,000 or a maximum of $750,000 per project per borrower and may
be used to finance design, installation, and implementation of an emission
control process. CLEAN was begun as a pilot program in the South Coast AQMD
and it has now been implemented throughout the state.
The Bay Area AQMD is working with the state Trade and Commerce Agency to
assist them in marketing their small business loan program, which offers loans
for environmental regulatory compliance. The district will help inform
businesses that the program is available. In addition, small business
economic assistance programs are being developed in Sacramento Metropolitan
AQMD, Mojave Desert AQMD, Santa Barbara County APCD, and the Bay Area AQMD.
V.
COMMENTS FROM CAPCOA/ARB PUBLIC WORKSHOP ON PERMIT STREAMLINING
This chapter contains comments made at the CAPCOA/ARB public workshop on
permit streamlining.
A. PURPOSE AND FORMAT OF THE WORKSHOP
On October 28, 1993, the CAPCOA and ARB jointly sponsored a public
workshop to discuss the various permit streamlining measures described in
this document and to obtain input from the regulated community on what
additional measures districts should implement and what priorities should be
placed on the different streamlining measures. Industry representatives
assisted in planning and conducting the workshop.
To provide a framework for discussions, presentations were made by
district and ARB staff on the following major streamlining elements: improved
communication with business, expedited permitting, assistance in submitting
applications and tracking progress, permitting manuals and streamlined
recordkeeping and reporting. In the afternoon, industry representatives
facilitated break-out sessions which stimulated constructive discussions.
B. COMMENTS ON IMPROVING THE AIR PERMITTING PROCESS
The following is a compilation of the workshop comments on how districts
could improve their permitting process, with a double asterisk (**) indicating
the suggested improvements that were voted by the participants as being
highest priority for implementation.
1. Improved Communication with Business
a. Work with economic development corporations
-There was support for California Environmental Protection Agency one-
stop permit centers and Business Environmental Assistance Centers
(BEACs).
-The roles of districts, ARB, and the U.S. Environmental Protection
Agency should be defined.
-Economic development corporations (EDCs) need to be educated on air
quality issues, not just sent air permit application forms and expected
to be able to help business.
-Bridges should be built between industry, districts and EDCs.
-EDCs should be a catalyst in developing partnerships.
b. Brochures and permit assistance materials
**There was support for brochures that explained the permitting process
and other district programs.
-Districts and industry should develop brochures in partnership.
-Model permit applications with standard conditions should be developed
with industry.
-Brochures should be industry specific.
c. Workshops and questionnaires
**Workshops should use a break-out format like this workshop.
-Districts should hold permit streamlining workshops.
-More compliance workshops and educational workshops by source category
would be helpful.
-The "we versus they" attitude should be avoided at workshops.
-District management should be at workshops so they can respond to
comments, but industry should not expect immediate decisions on all
issues.
-Effort should be made to increase attendance at workshops; trade
associations and affected industries should be involved early in the
rule development process.
-Make sure workshop notices, etc. are sent to all affected parties,
including city, county and other permit holders, not just the most
obvious businesses.
d. Small business assistance programs
-Small business assistance programs need to be better publicized.
-These programs should identify other resources and industry support
contacts, such as trade associations and chambers of commerce.
-Business assistance programs should avoid taking business away from
consultants; districts shouldn't increase in size just to support
improved communication.
e. General comments on improved communication
**Regulatory agencies need to improve communication, adopt a "customer
service" attitude, a non-adversarial approach.
**Participants would like districts to have E-mail.
**District regulations, permit handbook, application forms, BACT, and EPA
federally enforceable rules (for Title V) should be on computerized
bulletin board (RWQCB has such a system).
**Districts should hold pre-meetings to get input on rule implementation
for permits.
-Districts and ARB should refer to "regulated community", not "business"
since city, county and other non-business entities are regulated.
-Districts should discuss up front exactly what is needed for permits
and why, to allow for negotiation between district and applicant.
-Mail should be delivered to the permitting staff more quickly. Checks
for permit fees should not be delayed in accounting.
-Phone calls to public information offices should be returned more
promptly.
-Good communication is a two way street; industry should talk with
districts before making financial decisions.
-Trade associations should develop unified positions on proposed rules.
2. Expedited Permitting
a. Tiered permitting for small, medium, and large sources
**There was support for the tiered permitting concept.
-Some participants felt expedited permitting should be based on
complexity of project, not emission rates.
-There was concern that too many quick-review applications may be filed
at once, and districts won't be able to meet the quick timelines.
-Districts with less staff than South Coast can't permit sources in 7
days.
-Expedited permitting begins when an application is complete; businesses
need to be educated on how to submit complete applications.
-Applications that contain unnecessary information slow the district's
review.
b. Over-the-counter permitting
-Over-the-counter permitting is only possible for large districts.
c. Use of computers
**There should be greater use of computers.
-Computers should be used by districts for processing permits and by
sources for submitting information to districts.
-Computer programs should be designed to avoid re-entry of data.
-Widely used uniform software and simple codes should be employed so
anyone can use it.
-Districts should start with something simple, and not wait to develop a
complex system.
-Personal computers are sufficient for small and medium districts.
-Instructions on how to complete an application should be on disk.
-ARB and districts should use "real programmers" not permitting staff.
-Spreadsheets used to expedite permitting should be developed for more
types of equipment.
d. Expedited permitting
**There was support for the idea of paying increased fees to have
expedited evaluation of certain permit applications if it would not
slow processing of other applications; a very large premium was
suggested to avoid all applications from being expedited in this way.
-Companies should prioritize their applications if they have several
applications being processed by a district at one time.
-Political pressure on districts for expediting specific permits should
be avoided.
e. Pre-certification
**The list of precertified equipment should be expanded.
**Pre-certification should be a statewide program, uniform from one
district to the next district; if one district pre-certifies equipment,
all districts should accept it. (Only large districts have the
manpower to pre-certify equipment.)
**Districts should focus permit conditions on emissions limitations;
applications should ask only for information necessary to establish
those emissions limitations.
-Pre-certification should be equipment specific, not specific to
facility type.
-Industry and suppliers should be included in the process.
-ARB should work more with industry and not do independent research on
equipment.
f. Other comments on expedited permitting
-Districts should have programs to certify private permit engineers,
like South Coast AQMD's program. Certified engineers would not only
fill out application forms, but also do the engineering evaluation, so
the district would only have to check the certified engineer's work
before issuing the permit.
-There should be more sharing of information among districts and with
the regulated community.
-Keep it simple.
-Equipment information and emissions data should be organized so it can
be used easily by the district and other permit applicants.
-Previous permits should be used as prototypes (case base approach in
South Coast AQMD).
-There should be more specific exemptions, like at South Coast AQMD.
-Applicants are willing to educate permit engineers about their
industry.
-Districts need to assign someone to study permitting to simplify, avoid
duplication, and reduce the level of detail required. They should get
outside help in this study.
3. Assistance in Submitting Applications and Tracking Progress
a. Standardized application forms
**Statewide standardized forms should be developed; forms should be
developed for specific types of equipment.
**Districts should ask only for information necessary to control
emissions.
-Multiagency forms would reduce the number of times applicants have to
fill out general project information.
-Smaller districts should take advantage of forms, etc. developed by
large districts.
-Standard application forms are of value to large operations with
frequent permit needs, not to sources who come in for a permit only
once.
-Criteria list of what is necessary for a complete application needs to
be made more specific.
b. Pre-application meetings
**Pre-application meetings are beneficial, more should be held.
-Pre-application meetings can be held over the phone.
-There should also be post-application meetings.
-Districts should have permit engineers available to handle walk-ins.
-Applicants should pay attention to what districts/regulatory agencies
want or hire experienced consultants.
c. Application tracking
**The ability to track applications is critical to business.
-There was a lot of support for Ventura County APCD's program of giving
applicants the application number and the name of the permitting
engineer, of acknowledging receipt of applications, and screening
applications for completeness.
-There should be a method for tracking delinquent applications.
d. Other comments on applications and tracking
**Districts should send out only one set of information requests. They
should simplify the information needed and avoid 11th hour requests for
more information.
-It would be helpful to have flowcharts for applications/permits and
explanations of how applicants can avoid common problems.
-District staff needs to be more responsive; they are often too busy
with other projects to respond to applicant questions.
-Districts should have a designated person to call small businesses that
file incomplete applications to help them complete their applications.
-Some participants were concerned that applications are deemed complete
when it is convenient for the district, not when they are actually
complete.
-There should be fewer levels of management between the permitting
engineer and the decisionmaker in large districts.
4. Permitting Manuals
a. Standardized policies and procedures
**There was strong support for districts to have standardized policies,
procedures and emission factors that are available to the regulated
community.
**CAPCOA/ARB should push for more consistency in permitting between
districts.
**Districts should advertise that permitting manuals are available.
-The Bay Area AQMD's handbook is good; more equipment should be
included.
-There is a need for greater consistency within districts (permitting
and compliance). District permitting engineers should follow their own
districts manuals and policies.
b. Best Available Control Technologies
-A CAPCOA/ARB bulletin board with BACT, etc., was suggested as a way to
keep more current than the manuals.
-Districts should be open to considering new technology for BACT.
c. Other comments on permitting manuals
-Participants wanted more districts to implement some of the
streamlining measures discussed at this workshop.
-Small districts should borrow from larger districts.
-RACT bulletin board/manual should be developed.
-There is a need to recognize that there are different requirements for
CEQA and district rules.
5. Streamlined Recordkeeping and Reporting
a. Simplified recordkeeping for smaller sources
**Recordkeeping should be simplified.
-There should be good reasons for requiring records and for the
frequency of data collection.
-Reporting requirements should be consistent with permit conditions, for
example for averaging times.
-Records should be kept in an appropriate location. Companies should
have flexibility where records are kept; they should be allowed to keep
records at company's central business office, even if it is out of the
district.
-Businesses should be allowed to use income tax returns or sales taxes
documentation as proof/indicator.
b. Automation for larger sources
-Electronic data filing should be available. It allows business to
enter data, have access for compliance, and print out or sent by
E-mail to districts.
-Companies should have the option to use sophisticated electronic
systems; they should not be required to use them since they can be very
expensive.
-There should be the option of providing qualifications and explanations
for variable data.
-Automation should focus on the source or process where it can be done
easily, not be dependent on the size of the source.
-P/Cs are okay, too.
c. Other comments on recordkeeping and reporting
-There should be simplified reporting forms for each type of source.
-All district reporting requirements should be integrated so a source
fills out only one district form.
-There should be uniform reporting forms for all districts.
-Reporting forms should be coordinated with other agencies.
-Records should be kept with the source, not sent to districts.
-Companies should be given the flexibility of different pollution
control options.
-Bar codes should be used.
-Facilities need more training so they know what information to keep and how.
-Facilities should assign one person the job of keeping records.
-There should be a single point of contact at the district.


