          RULE 209 Conditional Approval - Adopted 4/18/72, Amended 1/9/89

          The Control Officer may issue an Authority to Construct or a
          Permit to Operate, subject to conditions to insure the compliance
          of the operation of any article, machine, equipment or other
          contrivance within the standards of Rule 208 and 208.1, in which
          case the conditions shall be specified in writing.  Commencing
          work under such Authority to Construct or operation under such
          Permit to Operate shall be deemed acceptance of all conditions so
          specified.  The Control Officer shall issue an Authority to
          Construct or Permit to Operate with revised conditions upon
          receipt of a new application, if the applicant demonstrates the
          article, machine, equipment or other contrivance can be operated
          within the standards of Rule 208 and 208.1 under the revised
          conditions.