NORTH COAST UNIFIED AIR QUALITY MANAGEMENT DISTRICT

REGULATION 5 -- Procedures for Issuing Permits to Operate for Sources Subject to Title V of the Federal Clean Air Act Amendments of 1990 [Reference: 40 CFR Parts 70.1,70.4,70.6(a)(6),70.7(a)(6) and 70.7(b)]

(Adopted December 10, 1993) (Amended November 21, 1994, May 18, 2001)



Chapter V -- DISTRICT ADMINISTRATIVE PROCEDURES


Rule 500 COMPLETENESS REVIEW OF APPLICATIONS

The Air Pollution Control Officer shall determine if an application is complete and shall notify the responsible official of the determination within the following time frames:

(a) For an initial permit, permit renewal, or a significant permit modification, within 60 days of receiving the application;

[Reference: 40 CFR 70.7(a)(4)]


(b) For a minor permit modification, within 30 days of receiving the application.

The application shall be deemed complete unless the Air Pollution Control Officer requests additional information or otherwise notifies the responsible official that the application is incomplete within the time frames specified above.

[Reference: 40 CFR 70.5(a)(2) and 70.7(a)(4)]