NORTH COAST UNIFIED AIR QUALITY MANAGEMENT DISTRICT

REGULATION 5 -- Procedures for Issuing Permits to Operate for Sources Subject to Title V of the Federal Clean Air Act Amendments of 1990 [Reference: 40 CFR Parts 70.1,70.4,70.6(a)(6),70.7(a)(6) and 70.7(b)]

(Adopted December 10, 1993) (Amended November 21, 1994, May 18, 2001)




Chapter -- VI PERMIT CONTENT

[Reference: 40 CFR 70.6]

Rule 635 COMPLIANCE SCHEDULE

A permit issued pursuant to Regulation 5 shall include a compliance schedule for any emissions unit which is not in compliance with current applicable federal requirements at the time of permit issuance, renewal, and modification (if the non-compliance is with units being modified). The compliance schedule shall resemble and be at least as stringent as that contained in any judicial consent decree, administrative order, or schedule approved by the District hearing board if required by state law and shall include the following requirements:

(a) A statement that the emissions unit will continue to comply with those permit conditions with which it is in compliance;

(b) A statement that the emissions unit will comply with any future applicable federal requirement on a timely basis;

(c) For each condition with which the emissions unit is not in compliance which addresses an applicable federal requirement, a schedule of compliance which lists all preventative or corrective activities, and the dates when these activities will be accomplished; and

(d) For each emissions unit that is not in compliance with an applicable federal requirement, a schedule of progress reports submitted no less frequently than semi-annually which include: 1) the date when compliance will be achieved, 2) an explanation of why compliance was not, or will not be, achieved by the scheduled date, and 3) a log of any preventative or corrective actions taken.

[Reference: 40 CFR 70.5(c)(8) and 70.6(c)(3)]