VENAPCD RULE 10 PERMITS REQUIRED

LAST REVISED 07/05/83

Rule 10. Permits Required (except as listed in Rule 23)

(Adopted 10/22/68, Revised 5/23/72, 11/21/78, 8/14/79,

7/5/83)

A. Authority to Construct

Any person building, erecting or installing any facility

including any article, machine, equipment or other

contrivance the use of which may cause the issuance,

reduction, control, or elimination of air contaminants, or

any person who plans any modification or replacement of any

facility or equipment which may alter the emissions of air

contaminants, shall first obtain written authorization for

such construction from the Ventura County Air Pollution

Control District. A separate permit application shall be

required for each non-contiguous property or location.

B. Permit to Operate

Before any person operates, uses or offers for use any

facility including any article, machine or other

contrivance, the use of which may result in the issuance,

reduction, control, or elimination of any air contaminant,

he first shall obtain a Permit to Operate from the Air

Pollution Control District. A separate permit application

shall be required for each non-contiguous property or

location.