VENAPCD RULE 14 TRIAL TEST RUNS

LAST REVISED 05/23/72

Rule 14. Trial Test Runs (Adopted 10/22/68, Revised and

Renumbered 5/23/72)

The applicant shall have the right to trial test run equipment

prior to application for, or receipt of a Permit to Operate,

provided the following procedure is followed:

A. Notify the Air Pollution Control District of the time,

place and the equipment involved in such trial test runs.

This notification is to be in writing and must be received

by the Air Pollution Control District at least seven (7)

days prior to such test run.

B. Trial test runs to be limited to twenty-four (24) hours in

any one calendar month. An Air Pollution Control District

representative has the right to be present at such trial

runs if he so desires.

C. Additional time beyond the twenty-four (24) hours in any

one calendar month can be granted only by the Air Pollution

Control District or by the Hearing Board.

D. Trial test runs of any piece of equipment that has not

been changed or rebuilt can be stopped at the discretion of

the Air Pollution Control District after a total of seventy-

two (72) hours in any three (3) calendar months.